Home › Home › Projects › Forth Replacement Crossing › About the proposals › timeline

Timeline

Transport Scotland is developing the FRC project in accordance with the customary planning and design process guidelines for major road schemes.

Key milestones for the project are:

Forth Replacement Crossing Milestones and Dates
Milestone NameMilestone Date
Construction ends and bridge opens to traffic 2016
Construction begins 2011
Construction tender awarded early 2011
Construction tender process begins Winter 2009
Parliamentary Bill introduced and Statutory Consultation
(see Bill Process)
Winter 2009
Environmental Impact Assessment concluded Summer 2009
Public Exhibitions Jan 2009
Scottish Government confirms scheme details Dec 2008
Ground investigations Mar - Aug 2008
Topographical surveys Mar - Aug 2008
Marine investigations May - Aug 2008
Traffic surveys begin Mar 2008
Land searches Feb 2008
Environmental surveys begin Feb 2008
Consultants appointed Jan 2008
Scottish Government confirms bridge crossing Dec 2007
Public Exhibitions August 2007
Forth Replacement Crossing Study Aug 2006 - June 2007
Visit Us On: Follow us on Flickr Follow us on Twitter Watch and subscribe to our YouTube channel

Please view the project contact details if you have an enquiry specific to the Forth Replacement Crossing project.

If you wish to make a more general enquiry, please view the information about Transport Scotland for details.


Forth Replacement Crossing logo