Use the list below to jump straight to the relevant M74 construction update:
East section
Structures
Auchenshuggle Bridge now has 100% of the deck waterproofed. All other structures are substantially complete. Under deck hard landscaping is substantially complete at Glasgow Road and about to commence at Farmeloan Road and Cambuslang Road.
Side Road
The main focus remains Cambuslang Road where works associated with Clyde Gateway are now complete enabling the completion of our works to be undertaken.
Earthworks
Bulk is complete, all formation is covered and planting well advanced and on target to be complete by end of season. The main emphasis moving forward remains tidying up soil and verges in order to maximise the early part of the seeding season.
Roadworks
Cement bound granular material (CBGM) is complete. No mainline bituminous surfacing was laid in the period.
The steel safety barrier, verge slabbing and central reserve concrete barrier are all well advanced with central reserve verge concreting progressing satisfactorily. Final surfacing and white lines will commence early April.
West section
Structures
M8/M74 Eastbound Link Bridge
Feature lighting and parapet rails commencing 2 April. Final road surfacing starting early April.
M8/M74 Westbound Link Bridge
Parapet rails and final surfacing commencing early April.
Port Eglinton Viaduct
Deck complete. Waterproofing to Port Eglinton Viaduct well underway, with sand carpet over half way complete.
Retaining Walls 12 and 15 (between Pollokshaws Road and Devon Place)
Backfill complete. CBGM sub base commencing mid March.
Strathbungo Railway Underpass
Deck cleaned off. Waterproofing starting early April.
Cathcart Road Bridge (Phase 2)
Facing brick starting mid March. Completion mid May.
Network Rail Access Road
Complete.
Final surfacing starting early April. Hard landscaping ongoing underneath.
Polmadie Underbridge, overlaid with base and binder course completed across the structure awaiting final surfacing.
Rutherglen Railway Station Bridge
Substantially complete.
Reinforced Earth Retaining walls
Substantially complete.
Pumping Station
Sheet piling complete.
Control Building brickwork complete. Facia boards, guttering, lightning protection, doors and louvres due to commence late March. Roof complete. power supply installation and Mechanical and Electrical work commences early April.
Earthworks
Planting is ongoing with all works planned for completion by end of March 2011.
Roadworks
M8 Westbound on ramp with kerbing now complete and sub base trimmed ready for surfacing which will complete base and binder from M8/M74 Westbound Link Bridge to tie-in with M8 outerbraid.
M8/M74 westbound Link kerbed and at binder level awaiting surfacing.
Kerbing on Gloucester Street complete.
Gloucester Street CBGM sub base complete.
Surfacing well underway with base and binder nearly completed and wearing course now started.
Continue to erect chainlink boundary fence on site with progress in line with programme to completion. Nearly half of fencing now completed.
Environmental barrier posts are nearly completed with barrier panels now erected at Polmadie, remainder to be complete mid April.
Central Reserve barrier substantially complete bar Cathcart cut.
Cathcart Cut westbound complete to binder level awaiting final surfacing, with eastbound at CBGM level except at Pumping Station.
Continuing to install comms hardstanding sites, foundations and cabling, with a completion date of mid May 2011.
Mainline lighting columns ongoing with all available columns and lanterns erected. Cathcart to Glasgow Road switch on anticipated early April.
Gantries – Seven to be erected. Completion anticipated in April.
High Mast Lighting at Kingston
All masts to be completed mid April
Side Roads – Kingston
Complete
Side Roads- General
Hard landscaping on-going under Polmadie Road Underbridge.
Aikenhead Road Junction due for completion end May.
Public Utilities
Final programme for Scottish Power connections agreed site wide, with works well underway.
Earthworks
The bulk of the earthworks is complete and all formation save 100m to the West of Rutherglen Station Bridge is covered. Planting is well advanced and on target to be complete by end of season. The main emphasis moving forward is tidying up soil and verges in order to maximise the early part of the seeding season.
Roadworks
Cement bound granular material (CBGM), like formation, is complete save 100m to the West of Rutherglen Station Bridge. No mainline bituminous surfacing was laid in the period, with a small quantity laid on access tracks and Cambuslang Road.
The steel safety barrier, verge slabbing and central reserve concrete barrier are all well advanced with central reserve verge concreting progressing satisfactorily. Towards the end of the coming period surface course and white lines will commence.
Structures
The main workface remains Auchenshuggle Bridge which has about half of the deck waterproofed. All other structures are at the stage where under deck hard landscaping is in progress ( Glasgow Road) or about to commence.
Side Road
The main focus remains Cambuslang Road where work associated with Clyde Gateway is being progressed. Upon their completion the remainder of our works will be undertaken.
West section
M8/M74 Eastbound Link Bridge
Verge concrete complete.
M8/M74 Westbound Link Bridge
Verge concrete complete.
Port Eglinton Viaduct
Deck substantially complete. Waterproofing underway.
Retaining Walls 12 and 15 (between Pollokshaws Road and Devon Place)
Substantially complete with joint sealant and concrete repairs ongoing.
Strathbungo Railway Underpass
No works carried out in period.
Cathcart Road Bridge (Phase 2)
Concrete foundations for brickwork complete.
Ground Beam at centre columns complete.
Concrete facings to piles ongoing, with spraycrete carried out between piles.
Network Rail Access Road
Substantially complete, but additional drainage required.
Polmadie Road Bridge
All waterproofing and sand carpet complete.
Rutherglen Railway Station Bridge
Substantially complete.
Reinforced Earth Retaining walls
Substantially complete.
Pumping Station
Sheet piling is underway. Construction of the Control Building is progressing, with brickwork due for completion in early March, roof slabs being placed 7 March, power supply installation 14 March and Mechanical and Electrical commences 21 March.
Earthworks and Roadworks
Earthworks
Gloucester Street embankment fully trimmed up to West Abutment, awaiting CBGM sub base.
Cathcart Cut westbound improvement layer is now trimmed awaiting CBGM, with eastbound awaiting completion of Pumping Station.
Planting is ongoing with all works planned for completion by end of March 2011.
Roadworks
M8 Westbound on ramp with kerbing now complete and sub base trimmed ready for surfacing commencing 24 Feb. which will complete base and binder from Westbound Link Bridge to tie-in with M8 outerbraid.
Kerbing on Gloucester Street embankment tied into Port Eglinton Viaduct West Abutment with kerbing on deck ongoing.
Waterproofing to Port Eglinton Viaduct and sand carpet underway.
PFA Backfill and improvement layer to Retaining Walls 12 and 15 complete awaiting CBGM sub base.
CBGM tied into Polmadie Underbridge, overlaid with base and binder course completed across the structure
Good progress on surfacing.
Continue to erect chainlink boundary fence on site with progress in line with programme to completion. Nearly a quarter of fencing now completed.
Environmental barrier posts are nearly completed with barrier panels now erected at Polmadie,
Central Reserve barrier (i.e.Concrete Safety Barrier) continue on site concreting transitions from CSB at Gantries and infill concrete on the central reserve.
Continuing to install comms hardstanding sites, foundations and cabling, currently showing a completion date of 20 May 2011.
Mainline lighting columns ongoing with all available columns and lanterns erected.
Pipelaying to Outfall Three on Polmadie complete with minor works to manholes and road reinstatement outstanding.
Gantries progress, in summary:
High Mast Lighting at Kingston
10 of 14 Masts erected, with all works due for completion by 4 April.
Side Roads – Kingston
Final testing of Street lights ongoing and progressing
Side Roads - General
Final surfacing on Polmadie Road under and adjacent to Polmadie Road Bridge now complete with major works at Aikenhead Road ongoing.
Hard Landscaping under Polmadie Road Bridge commenced 14 February 2011.
Public Utilities
Final programme for Scottish Power connections agreed site wide, with works well underway.
East section
The construction works continue to move in a linear fashion from West to East along the route.
Verge slabbing has reached the East end, environmental barrier work on some structures is complete, as is the central reserve barrier. Landscaping and tree planting is well advanced. Boundary fencing is on programme.
At Auchenshuggle the final parapets are cast and the falsework is being removed.
At Rutherglen Station Bridge backfilling to the west side is underway, whilst kerbing is ongoing on the east. The gantry base immediately west of the bridge has commenced.
On the side roads, works are concentrated at Cambuslang Road, where a Clyde Gateway closure is assisting in reducing traffic and increasing the available work area.
In summary, the section remains on course to be completed on programme.
West section
M8/M74 Eastbound Link Bridge – Substantially complete.
M8/M74 Westbound Link Bridge – Substantially complete
Port Eglinton Viaduct – Deck and parapet construction ongoing. Deck complete except for the concreting of the central gap between the eastbound and westbound carriageways. Parapets 50%. Waterproofing 30%.
Retaining Walls 12 and 15 (between Pollokshaws Road and Devon Place) – Substantially complete.
Strathbungo Railway Underpass – Substantially complete.
Cathcart Road Bridge (Phase 2) – Wingwall and abutment facing construction progressing. Construction of centre column ground beam commenced.
Network Rail Access Road – Substantially complete.
Polmadie Road Bridge – Substantially complete.
Rutherglen Railway Station Bridge – Final concrete works ongoing (ground beams etc) plus finishes and clearance.
Reco Retaining walls – Substantially complete.
Pumping Station –Construction of the Control Building is progressing.
Earthworks and Roadworks –
Earthworks
Removal of the earthworks “plug” at Cathcart Cut is now complete with all improvement layer material placed, awaiting final trim.
Surcharge on Gloucester Street (Kingston embankment) has also been removed with topsoil placed on adjacent landscape areas.
Grass seeding complete to most available areas. Planting is ongoing with all works planned for completion by end of March 2011.
Roadworks
No mainline surfacing works carried out this month. All available areas of mainline roads complete to binder level, with surfacing progress currently, base 82%, binder 65% and wearing course 2%.
The sand carpet protective layer over the bridge deck waterproofing has commenced at Port Eglinton Viaduct, with Polmadie Road Bridge surfacing due to commence in early February.
Permanent fencing at Network Rail locations is complete, and progress with the chainlink boundary fencing is in line with the programme for completion. Over 25% of all fencing now completed. Environmental barrier posts are nearly completed.
Re-commenced transition CSB (Concrete Safety Barrier) at Gantries and infill concrete on the central reserve.
Installation of comms hardstanding sites and foundations ongoing on programme. Mainline lighting ongoing, with first sections at Polmadie due to be illuminated in February.
Pipe laying to Outfall 3 on Polmadie ongoing.
Gantries progress, in summary:-
Side Roads – Kingston
All surfacing to Kingston roads now complete, with footpath surfacing also substantially complete.
Street lights and new traffic lights are substantially complete, as is hard landscaping at eastbound and westbound link bridges on Carnoustie Street.
Sign foundations and sign erection is also substantially complete with sign fabrication ongoing
Side Roads- General
Work to all other side roads is programmed to be carried out between now and May 2011.
Final surfacing on Polmadie Road at Polmadie Road Bridge is ongoing with major works at Aikenhead Road due to commence in the second week of February 2011.
Hard Landscaping under Polmadie Road Bridge also due to commence in the second week of February 2011.
East section
Earthworks
The earthworks team has been moving from west to east remediating verges, topping up drains and finalising the available planting areas.
In addition the access tracks around Clydebridge Steelworks have been progressed to formation level.
Roadworks
In this section works continue to progress in an easterly direction with surfacing at binder level, lighting columns erected, verge slabbing and safety barrier ongoing. In addition the concrete central reserve barrier has progressed beyond Cambuslang Road.
Structures
All bridges save Auchenshuggle Bridge – substantially complete bar parapet metalwork and under deck hard landscaping.
Auchenshuggle Bridge – deck parapet walls nearing completion.
West section
M8/M74 Eastbound Link Bridge – Substantially complete.
M8/M74 Westbound Link Bridge – Substantially Complete
Port Eglinton Viaduct – Final structural steelwork connections complete. Deck and parapet construction complete from West Abutment to Span 7, along with launches and a first deck pour towards the east end (approx 60% of total). Permanent formwork now complete, and steel reinforcement to deck nearly complete.
Retaining Walls 12 and 15 (Between Devon Place and Pollokshaws Road) – One wall infill panel left out for plant access to area now near completion. Backfill between walls approximately 90% complete, with completion due for mid December 2010.
Strathbungo Railway Underpass – Substantially complete.
Cathcart Road Overbridge (Phase 2) – Deck complete. Wingwall and abutment facing construction is in progress, removal of earthworks “plug” well underway.
Network Rail Access Road – Substantially complete.
Polmadie Road Bridge – Substantially complete.
Rutherglen Railway Station Bridge – Deck substantially complete. Parapets 90% complete.
(Reco) Retaining walls – Substantially complete.
Earthworks -
Removal of “plug” at Cathcart Cut underway, with 12000m3 of clay still to be removed.
Surcharge at Kingston has been released with topsoil surcharge being placed on Gloucester Street embankment.
Grass seeding complete to all available areas, except area adjacent to West Section offices, which is currently receiving clay from Cathcart Plug.
Planting has now commenced with all planting works planned for completion by end of March 2011.
Roadworks -
No mainline surfacing works carried out this month with all available areas of mainline roads complete to binder level, with surfacing progress currently, base 82%, binder 65% and wearing course 2%.
Sand Carpet (bituminous protective layer to deck waterproofing) has commenced at Port Eglinton Viaduct, with surfacing of Polmadie Road Bridge imminent.
Permanent fencing at Network Rail locations is complete, and chainlink fence progressing, with 24% of fencing now completed. Environmental barrier posts remain at 87% completed.
Concrete Safety Barrier (CSB) complete from Cathcart Road to Southcroft Road, excluding the deck of Polmadie Road Bridge.
Comms hardstanding sites and foundations ongoing.
114 lighting columns now erected and lantern installation now ongoing.
Gantries progress, in summary -
Side Roads – Kingston
Wearing Course on Carnoustie St, Dalintober St, Cook Street, West Street and Wallace Street is complete and final section at Scotland Street/Carnoustie Street completed this period.
New Street lights are now lit where available, with new Traffic Lights substantially complete at all Kingston junctions.
Hard Landscaping is ongoing at the M8/M74 eastbound link bridge with the westbound link bridge substantially complete.
Side Roads- General
All other side roads beyond the Kingston Area programmed to be carried out between January and May 2011.
Public Utilities
West section
M8/M74 Westbound Link Bridge - Substantially Complete
Port Eglinton Viaduct - Final structural steelwork connections are near completion. Deck and parapet construction complete from West Abutment to Pier 5 (approx 45% of total). Permanent formwork and reinforcement continuing beyond this point.
Retaining Walls 12 and 15 (Devon Place) - One wall infill panel left out for plant access to area now underway. Remainder substantially complete. Load Transfer platform is complete with backfill now approximately 90% complete, with completion due for mid December 2010.
Strathbungo Railway Underpass - Substantially complete.
Cathcart Road Bridge (Phase Two) - Deck complete. Wingwall and abutment facing construction is in progress.
Network Rail Access Road - Substantially complete.
Polmadie Road Bridge - Substantially complete.
Rutherglen Railway Station Bridge - Deck substantially complete. Parapet construction is ongoing.
Reco Retaining walls - Substantially complete, with copes to Wall 4 (at M74/M8 westbound link viaduct) installed this month.
Earthworks and Roadworks - Earthworks, substantially complete at Kingston with removal of "plug" at Cathcart Cut now underway. Surcharge at Kingston is showing signs of levelling out and should be released soon. Topsoiling and grass seeding complete to most available areas. Grass is now growing in landscaped areas and appears to be well established.
All available areas of mainline roads are complete to binder level, including Strathbungo, Cathcart Cut (excluding the "plug"), Polmadie East and West and Polmadie off and on slips.
Surfacing has been carried out both eastbound and westbound, including binder layer over eastbound and westbound M8/M74 Link Viaduct and base and binder to the eastbound Dalintober Street on ramp.
Surfacing progress is currently, base 82%, binder 65% and wearing course 2%
All available safety barrier completed, with over 3600m currently installed, leaving 40% outstanding.
Permanent fencing at Network Rail locations is ongoing. Environmental barrier posts are 87% completed.
Comms hardstanding sites continuing. Comms ducting is 54% complete, Lighting ducts are also 62% completed and 88 lighting columns now erected and cabling underway.
Gantries progress, in summary:
Side Roads - Surfacing at Carnoustie St, Dalintober St, Cook Street, West Street and Wallace Street are complete to wearing course level, with only final section at Scotland Street/Carnoustie Street outstanding.
Street lighting and Traffic Light ducting remains at 90% completed and columns are 50% completed.
East section
Earthworks - Resoiling is now well advanced.
Roadworks -Surfacing at binder level (i.e. level below final 35mm wearing course) throughout except Rutherglen Station and Auchenshuggle bridges
Drainage -Matching roadworks progress.
Pavements -During the period mainline pavement has progressed well.
Side Roads
Glasgow Road -No work in the period.
Cambuslang Road - Following SP diversion, footpath construction has now commenced.
Fullarton Roundabout -Roundabout reconstruction carried out.
Structures
Glasgow Road -PCA (Pre-completion Audit) and finishes ongoing.
Cambuslang Road Bridge -PCA and finishes ongoing.
Auchenshuggle Bridge - Deck construction complete, parapet construction ongoing.
Fullarton Road - PCA and finishes ongoing.
For previous reports, see Construction Progress Archive
West section
M8/M74 Eastbound Link Bridge - Structure is substantially complete with finishes outstanding. Blacktop is completed to binder level (only final surface outstanding). Hard landscaping (slabs etc) preparation is underway.
M8/M74 Westbound Link Bridge - Blacktop is completed to binder level and hard landscaping is underway.
Port Eglinton Viaduct - All substructure works now completed to both decks. Deck concreting has re-commenced. Waterproofing has commenced to the west end of deck.
Steel erection from Pier 10 to East abutment has been completed with remaining steelwork on eastbound deck from piers 7-9 underway. Steel erection will be completed mid-October with secondary steelwork and painting touch-ups continuing.
Brickwork cladding is substantially complete at the east abutment. Outstanding brickwork cladding to west abutment wingwalls and final panel at east abutment will re-commence in next period.
Retaining Walls 12 and 15 (between Job Centre and St Andrews Printworks) - Pre-cast piling is completed. Earthworks fill has commenced
Strathbungo Railway Underpass - Approach parapets will commence following backfill to structure.
Cathcart Road Bridge (Phase 2) - The remainder of deck is now concreted. Wingwall preparation is ongoing. Reinstatement of final gas diversion into deck has commenced which in turn will allow the removal of final earthworks.
Network Rail Access Road - Road box is now surfaced to binder level. Only final surface to be laid.
Polmadie Road Bridge - Parapet upstands are now completed and finishes will commence in next period.
Rutherglen Railway Station Bridge - All substructure works are now substantially completed. First four deck pours of 16 are concreted with rebar progressing ahead. Most of deck pours are controlled by possession access restrictions and main deck will be completed in October with parapet upstands to follow.
Reco Retaining walls - Wall 9(Kingston) is now complete with installation of copes now finished. Fencing etc to top of walls will start in next period.
Earthworks and Roadworks - Earthworks are on-going at Kingston, with imported topsoil as surcharge now complete. Topsoiling continues with extensive areas available and prepared for landscaping, including the bunded area behind the Travelodge.
All available areas of mainline roads are complete to binder level, including Strathbungo, Cathcart Cut (excluding the "plug"), Polmadie East and West and Polmadie off and on slips.
Next concrete based granular material (CBGM)/surfacing visit has commenced eastbound and westbound, excluding surfacing over the M74/M8 eastbound and westbound link viaducts. CBGM is now 78% completed.
Surfacing progress is currently, base 82%, binder 65% and wearing course 2%
Commenced mainline safety barrier, with over 3000m currently installed and works ongoing. This leaves 48% outstanding.
Permanent fencing at Network Rail locations is ongoing. 20% of fencing is now completed. Environmental barrier posts are 50% completed.
Continue to install comms hardstanding sites. Comms ducting is 50% complete, Lighting ducts are also 58% completed and a nominal start has been made to columns.
Gantries progress, in summary:-
Side Roads - Surfacing at Carnoustie St and Dalintober St are complete to wearing course level, West St and Scotland St are completed. Wallace St ongoing at weekends.
Street lighting and Traffic Light ducting remains at 90% completed and columns are 50% completed.
East section
Earthworks
River Clyde- Resoiling to batters (sideslopes) and verges is well advanced, as is the seeding element of soft landscaping.
Tie-in - Here, batters have been trimmed and resoiled during this period. Verges have yet to commence.
Roadworks
Rutherglen - Verge finishes are substantially complete with only lighting columns outstanding.
River Clyde - In this area near completion of binder layer. Verge slabs, safety fencing and environmental barrier all continue.
Tie-in - Progressing road base.
Drainage, Ducting and Comms
Keeping pace with earthworks and roadworks.
Side Roads
Cambuslang Road - Scottish Power continue with their diversion.
Structures
Cambuslang Road - The deck has been waterproofed, sandcarpeted and surfaced. Concrete finishing is progressing.
Auchenshuggle Bridge - The bridge deck has been cast.
East section
The highlight of the month has been completion of cement bound granular material (CBGM) except for 50 metres to the west and 20 metres to the east of Rutherglen Station Bridge.
Earthworks
Rutherglen Station
During the period the area previously occupied by the soil hospital adjacent to Southcroft Road has been cleared and shaped. In addition verge soiling has commenced and batter weed killing/cultivation is ongoing.
Farmeloan Road
Here in the period the surcharge was removed, used as special fill behind the east abutment of Rutherglen Station, before formation being made and follow on roadworks commencing.
River Clyde
Between these chainages, verge filling is ongoing, landscape area shaping and soiling has commenced. In addition the Corus access tracks have been constructed to formation level.
Tie-in
This area is the last ‘dirty' part of the site with infill being moved into its final position. In addition verge and central reserve fill is ongoing.
Roadworks
Rutherglen Station
Verge finishes are ongoing in this area, with the next task being central reserve barrier.
River Clyde
At the west end of this area, the CBGM sub base between Farmeloan and Rutherglen (east) has been laid, whilst elsewhere we are working eastwards progressively reaching binder level. Verge safety barrier has commenced at the west end of this area.
Tie-in
Here the CBGM has been completed and kerbing is ongoing.
Drainage
Keeping apace with earthworks and roadworks.
Pavements
During the period mainline pavement has progressed well across the east section.
Side Roads
Glasgow Road
During the period the Borglas Access was kerbed. No other works were undertaken.
Cambuslang Road
Scottish Gas Continue their work, whilst Scottish Power have commenced onsite.
Structures
Glasgow Road Underbridge
The inspection galleries have been finished and waterproofed.
Farmeloan Road Underbridge
The deck has been waterproofed, kerbed and surfaced.
Cambuslang Road Underbridge
The deck waterproofing is ongoing, approximately 60% complete. Under deck temporary works at the abutment have been concrete finished. Finishing to the piers and diaphragms are ongoing.
Auchenshuggle Underpass
The underpass invert has been waterproofed and the first QA completion inspection carried out.
Auchenshuggle Bridge
Steelwork moved into position allowing progress to be made on the deck ends. Reinforcement is well advanced on the deck, with the first of five pours scheduled for early September.
Fullarton Road
Deck waterproofing carried out in the period.
West section
M8/M74 Eastbound Link Bridge
Structure is substantially complete with finishes outstanding. Waterproofing and sand carpet have been completed.
M8/M74 Westbound Link Bridge
Parapet approaches and waterproofing are now complete.
Port Eglinton Viaduct
All substructure works completed to westbound deck. Remaining columns under the launch 2 position are now completed. No substantial progress in period on deck construction pending further structural steel erection, although final stripping of cantilever falsework at west end is progressing well, and preparatory works for waterproofing have commenced in this area also.
Steel erection from Pier 7 and the westbound launch has been completed as well as eastbound from Pier 5 to Pier 7. This has allowed a re-start to steel reinforcement to this area and next deck concrete pour is programmed for week commencing 30 August.
Brickwork cladding is substantially complete at the east abutment. Outstanding brickwork cladding to west abutment wingwalls and final panel at east abutment will re-commence in next period.
Retaining Walls 12 and 15 (Devon Place)
Pre-cast piling is complete with 45% of mushroom heads (which top the driven piles) constructed. Earthworks fill to commence in next period. .
Strathbungo Railway Underpass
Approach parapets will commence following backfill to structure.
Cathcart Road Bridge (Phase 2)
The remainder of deck is programmed for concreting on 30 August. Wingwall preparation is underway. Reinstatement of final gas diversion into deck will commence soon which in turn will allow the removal of final earthworks ‘plug' .
Network Rail Access Road
Road box is now surfaced to binder level.
Polmadie Road Bridge
Remainder of deck concrete has been completed and works have commenced to parapet.
Rutherglen Railway Station Bridge
All substructure works are now substantially complete. First two deck pours of 16 are programmed for week commencing 30 August with rebar progressing ahead. Formwork panel installation has been completed.
Reco Retaining walls
Wall 9(Kingston) is now complete with installation of copes now finished.
Earthworks and Roadworks
Earthworks are on-going at Kingston, with imported topsoil as surcharge now complete. Surcharge removal will recommence in next period. Topsoiling continues with extensive areas available and prepared for landscaping, including the bunded area behind the Travelodge at the M74/M8 eastbound link viaduct.
All available areas of mainline roads are complete to binder level, including Strathbungo, Cathcart Cut, excluding the "plug", Polmadie East and West and Polmadie off and on slips.
.
CBGM/Surfacing has commenced at Kingston end eastbound and westbound, excluding surfacing over the eastbound and westbound link viaducts. CBGM is now 78% completed in the west section.
Surfacing progress is currently, base 75%, binder 58% and wearing course 8%
Over 3000m safety barrier currently installed and works ongoing. This leaves 48% outstanding.
Permanent fencing at Network Rail locations is ongoing with further resource programmed to commence mid August 2010. 15% of fencing is now completed. Environmental barrier posts are 50% completed.
Comms hardstanding sites continue to be installed. Comms ducting is 50% complete, Lighting ducts are also 58% completed and a nominal start has been made to columns.
Gantries progress, in summary:-
First two gantries removed and replaced with temporary signage. One gantry has been removed for alterations and one altered in position. Three are still to be removed and five to be altered insitu. Fit out works underway and three finished.
Work underway with all gantries, with fabrication of three outstanding, to be completed soon. Some legs are now with painters.
Side Roads
Surfacing at Carnoustie St and Dalintober St are complete to wearing course level, West St is 50% and Scotland St is 75% completed. Road closures are agreed for 11 Sept and 23 Sept to allow access to Wallace St and Cook St areas.
Street lighting and Traffic Light ducting remains at 90% completed and columns are 50% completed.
The majority of the major structures along the whole of the M74 Completion project are now in place but significant work remains to be done to ensure the new road meets its programmed opening in August 2011.
West Section
The M8/M74 Link Bridges are practically complete. On the eastbound bridge, only the finishing touches such as surfacing, stainless steel parapet rail and expansion joints remain to be added. Waterproofing of the structure has been completed and the protective sand carpet which will allow access over the bridge for roadworks west of the deck has been laid.
The parapet approaches and waterproofing have been completed on the westbound bridge.
All substructure works have been completed to the westbound deck of the Port Eglinton Viaduct. Remaining substructure works to columns under the eastbound carriageway are progressing well with only two columns remaining.
Further structural steel will go up before further deck construction work is undertaken, although final stripping of cantilever falsework at the west end of the structure is progressing well, and preparatory works for waterproofing have commenced.
Steel is in place from pier 10 to the east abutment on the westbound deck and is in the process of being erected between pier 7 and the westbound launch. Brickwork cladding is substantially complete at the east abutment.
Pre-cast piling at Retaining Walls 12 and 15 (Devon Place) is progressing and two-thirds of the piles have been driven to date.
Approach parapets will commence after backfilling to the Strathbungo Railway Underpass.
The north and south abutments have now been cast for the second phase of work at Cathcart Road Bridge and installation of the falsework support for the deck is in progress.
The road box is now surfaced to binder level at the Network Rail Access Road, which leaves only final surfacing (35mm thick) to be done.
All pre-cast beams have now been installed at the Polmadie Road Bridge and the first of three deck pours has been completed. Reinforcement steel work and formwork are continuing for the second deck pour.
At Rutherglen Railway Station Bridge, all substructure works are now substantially complete, and structural steel is in place. Cantilever falsework has been completed and formwork panels are in the process of being installed. Final fixing and grouting of bearings is well under way to allow reinforcement to go ahead.
The Kingston Reco retaining wall is now complete with just the wall coping (finishing slab) outstanding.
Earthworks are on-going at Kingston, and topsoiling continues with many areas ready for landscaping, including the bunded area behind the Travelodge near the start of the project.
All available areas of mainline roadworks are complete to binder level, including Strathbungo, Cathcart Cut, excluding the "plug" which will be excavated on completion of Cathcart Road overbridge, Polmadie East and West and Polmadie off and on slips.
The next phase of cement bound granular material (CBGM) and surfacing work was set to commence in late July eastbound and westbound, with surfacing due to take place over both the east and westbound M8/M74 link bridges.
Following this work, around 3500m3 of CBGM and 12000 tonnes of base and binder will remain to be laid before the wearing course along the entire route.
Work to install mainline safety barriers has commenced, with over 2000m currently in place. Permanent fencing at Network Rail locations is ongoing, as is installation of hardstanding sites for communications maintenance vehicles. Installation of overhead gantry signs is progressing.
Along the side roads, surfacing at Carnoustie Street and Dalintober Street has been completed to wearing course level, with works to the remaining Kingston side roads due to be completed.
Street lighting and traffic light ducting is 90% completed at both Kingston and Polmadie Road, with 46 of the 53 road crossings now complete.
East Section
At the east end of the project, the highlight of the past month was the opening the Auchenshuggle cycleway, which has allowed the temporary pedestrian walkway across the site to be removed.
Meanwhile, mainline surfacing has been completed on Glasgow Road Bridge, with the deck waterproofed and galleries concrete finished.
Work continues on the embankments between Farmeloan and Rutherglen, and to the west side of Rutherglen Station Bridge.
At Glasgow Road, the railway access track has been constructed to sub-base level and mainline verges have been prepared for roadwork finishes. These roadworks have been completed to binder level on both carriageways, with work commencing on the safety barrier and verge paving. The area has also been planed out, re-kerbed and resurfaced and work is progressing to construct a new access to the Borglas facility.
The area between the existing embankment and the west abutment at Rutherglen Station has been filled.
Mainline CBGM and slip road surfacing to binder level have been completed at the River Clyde, with kerbing work set to follow.
Excellent progress has been made between Fullarton Roundabout and Carmyle, with road formation completed, the Auchenshuggle Bridge east abutment backfilled and batter trimming and soiling ongoing. Mainline CBGM is ongoing and new traffic signals on Fullarton Roundabout have been switched on.
Scottish Gas has been diverting its pipes at Cambuslang Road and Scottish Power will divert its infrastructure before roadworks can start. The reinforced concrete parapets have been cast and the deck has been cleared prior to waterproofing preparation at Cambuslang Road Bridge.
The substructure masonry is continuing at Auchenshuggle Bridge, as is the deck reinforcement. Cleveland Bridge is using jacks to move the beams to their final positions. Progress has been made on the parapet approaches.
The decks have been cleared at Fullarton Road and are awaiting waterproofing.
West Section
The highlight of the period was the successful launch of the eastbound carriageway of the main span of Port Eglinton Viaduct.
M8/M74 Eastbound Link Bridge - Structure is substantially complete with finishes outstanding. Waterproofing is now completed with protective sand carpet started and this will allow access over bridge for roadworks west of deck
M8/M74 Westbound Link Bridge - Parapet approaches and waterproofing are at same stage of completion as Eastbound Link described above.
Port Eglinton Viaduct - All substructure works are now completed to westbound deck. The only remaining substructure works is to columns under the launch 2 position (eastbound carriageway). These columns and breaking out of temporary concrete walls were underway soon after the start of launch 2.
Deck formwork panels are now complete to pier 5/6 (Mauchline Street) Steel reinforcement is also complete to pier 5/6. Deck sections have now been concreted and we are tight behind steel erection. Similarly insitu parapets are advancing well and are closely following main deck pours. Concrete in this area is now stalled awaiting extension to the steel beams. Concrete to deck will re-commence in 4/5 weeks time.
Launch 2 commenced as programmed and is now completed. Steel erection from pier 5 to connect to pier 7 (Mauchline Street) is now completed to the westbound deck. This section stops short of launch rear by 2 spans and infill beams are now on-site for site lengthening and erection. This stage will start erection in July.
Pier 10 (Devon Street) to East Abutment now ready to erect and preparation is underway with temporary trestles in position. This section cannot be concreted until full length of steel beams in place. Brickwork cladding has now almost completed at east abutment.
Retaining Walls 12 and 15 (Devon Place) - Pre-cast piling has started with good progress being made. Piling is 35% completed and we are looking to start mushroom heads (pilecaps) ahead of programme ie before piling is completed.
Strathbungo Railway Underpass - Approach parapets will commence soon following backfill to structure which is almost complete.
Cathcart Road Bridge - Stage 2 piling is now completed with trimming and preparation for stage 2 deck now underway.
Network Rail Access Road - Road box is now surfaced to binder level, which leaves only final surfacing (35mm thick) to be done.
Polmadie Road Bridge - Beams for span 1 and 2 are now placed with deck construction ongoing to one third of deck. Span 3 and 4 deliveries have now commenced with erection planned for start on 2 July.
Rutherglen Railway Station Bridge - All substructure works are now substantially complete. Steel erection has been completed to 16 primary beams with good progress being made on secondary bracing. Deck formwork panels are now underway as is cantilever formwork. Steelfixing will start next week. Precast embankment piles behind the west abutment are complete and structural and embankment fill about 50% completed.
Reco Retaining walls - Wall 9(Kingston) is now complete with a nominal section remaining awaiting final settlement of extended fill area. Second phase of wall 9 is almost completed following final settlement period.
Earthworks and Roadworks - Earthworks is on-going at Kingston. Bulk fill behind west abutment is now 100% completed with some surcharge material in place. This surcharge has used capping material which is now being repositioned locally. PFA (pulverised fuel ash) has been completed to structure and remainder of surcharge requirement will be using imported topsoil which again will be repositioned locally after sufficient settlement has taken place. 90,000 sq m of capping has been placed to date.
Earthwork at Strathbungo is now trimmed to roadbox after drainage completed.
Cathcart cut is complete except ‘plug' for road diversion. Following completion of piling to stage 2 of Cathcart Road bridge some excavation to reduce ‘plug' volume has started. CBGM sub-base (Cement Bound Granular Material) has completed to Polmadie tie-ins, Strathbungo mainline and Cathcart Cut. All CBGM has been covered to binder level.
Mainline Roadworks has progressed well with 26,000t of CBGM now placed. Blacktop protection of CBGM has followed to binder level. On and off ramps at Polmadie are complete to binder level. Polmadie side road is 100% to binder level.
Side Roads - 90% progress at Carnoustie St and Dalintober . Street lighting and Traffic Light ducting is 90% completed at both Kingston and Polmadie Rd. 44 of 51 road crossings are now complete.
East section
The highlight of the period was lifting beams onto Auchenshuggle Bridge. Detailed progress to date follows:-
Earthworks
Topsoiling to batters (sideslopes) was completed in the period and landscaping commenced with cultivating and seeding.
Again batters have been soiled and the south batter handed over to the soft landscaper. In addition following completion of the Rutherglen Bridge west abutment, backfilling has recently commenced.
No work during this period, consolidation continues with over one metre of settlement having occurred to date.
Here, the final trim of foundation, verge fill and limited resoiling was carried out in the period.
Again the final trim of foundation was carried out and the access tracks to the west of the mainline commenced.
No work in the period while the Auchenshuggle Bridge beams were in the lay down area. Work will commence in earnest now that beams have been removed.
During this period, formation, verge fill and batter topsoiling have all been undertaken in this area.
| Activity | % Complete |
|---|---|
| Drainage | |
|
Pre- earthworks |
90 |
|
Mainline |
92 |
|
Gully pots |
90 |
| Pavement | |
|
Formation |
88 |
|
CBGM sub-base |
53 |
|
kerbing |
27 |
|
Bituminous roadbase |
11 |
| Ducting | |
|
Motorway comms |
66 |
|
Street lighting |
61 |
| Env barrier posts |
74 |
Structures
No work in the period, awaiting deck waterproofing prior to bituminous pavement train arriving.
During the period the parapet walls have progressed.
Area cleared and finishes progressed.
Substructure masonry progressed and superstructure beams landed.
West Section
M8/M74 Eastbound Link Bridge - Structure is substantially complete with finishes outstanding. Waterproofing is now completed and will allow access over bridge for roadworks west of deck.
M8/M74 Westbound Link Bridge - Backfilling is now complete. Parapet approaches are almost completed with waterproofing now started as with Eastbound Link Bridge.
Port Eglinton Viaduct - All substructure works are now completed to westbound deck. The only remaining substructure works is to columns under the launch 2 position.
Formwork panels are now complete to pier 5. Steel reinforcement is complete to pier 5/6. Deck sections have now been concreted and we are almost tight behind steel erection. Similarly, parapets are advancing well and are closely following main deck pours. Launch 2 is concreted with parapets and awaits final temporary works to commence movement on 4th June as programmed.
Steel erection from pier 5 to connect to pier 7 is now completed to the westbound deck. This section stops short of launch rear by 2 spans and infill beams are now on-site for site lengthening and erection.
10 of 10 steel beams for pier 10 to East Abutment now on site to be lengthened for erection in June. This section will commence once resources are free from Launch 2 preparation.
Brickwork cladding has now been completed at west abutment. Team has now started at east abutment.
Retaining Walls 12 and 15 (opposite the Job Centre in Devon Place) - Walls have been concreted with gap panel remaining. Parapets are completed with earthworks underway to piling platform. Driving pre-cast piles is programmed to follow on 2 June with a 9 week duration.
Strathbungo Railway Underpass - Approach parapets will commence following backfill to structure.
Cathcart Road Bridge - Stage 2 piling has progressed well with 44 of 54 piles now completed. This operation should be completed first week in June followed by two weeks of trimming and preparation for stage 2 deck.
Network Rail Access Road - Road box is now shaped up with kerbing started.
Polmadie Road Bridge - Beams are now fully delivered for span 1 and 2 with erection starting 28 May 2010. Span 3 and 4 deliveries will now commence with erection planned for late June.
Rutherglen Railway Station Bridge - All substructure works are now substantially complete. Steel erection has been completed to 16 primary beams with good progress being made on secondary bracing. Structural and embankment fill imminent.
Reco Retaining walls - Wall 9(Kingston) is now complete with a nominal section remaining awaiting final settlement of extended fill area.
Earthworks and Roadworks - Earthworks are on-going at Kingston. 12,000 cubic metres of fill has been placed to extend embankment towards west abutment of Port Eglinton Viaduct. Bulk fill behind west abutment is now 100% completed with some surcharge material in place. PFA (Pulverised Fuel Ash - residue from coal fired power stations), which is used as lightweight fill material, has been completed to structure. 90,000 square metres of capping has been placed in period.
Earthwork at Strathbungo is now trimmed to roadbox after drainage completed.
Cathcart cut is complete except ‘plug' for road diversion. CBGM (cement bound granular material) has started to Cathcart cut following Polmadie tie-ins and has extended over to Strathbungo mainline. All CBGM has been covered with blacktop to binder level (35mm below finished road surface level).
Mainline Roadworks have progressed well with 26,000 tonnes of CBGM now placed. Blacktop protection of CBGM has followed to binder level. Next visit of CBGM will include tie-ins to west of bridges and Kingston embankment.
On and off ramps at Polmadie are complete to binder level. Polmadie side road is 100% to binder level.
To date, west section completion percentages are, CBGM 61%, Base 68% and Binder 50%.
Side Roads - 30% progress at Carnoustie St and Dalintober St. Street lighting and Traffic Light ducting is 90% completed at both Kingston and Polmadie Rd.
East Section
Earthworks
Glasgow Road - Topsoiling to sideslopes, and drain top up and toe of sideslopes has commenced.
Rutherglen Station - At this location formation was trimmed during the period, sideslopes are already soiled (save the area adjacent to Rutherglen West abutment) and the toe of sideslope tidy will progress easterly upon completion of Glasgow Road.
Farmeloan Road - This area is presently under surcharge and settlements are ongoing.
Cambuslang Road - Here, final trim of formation has progressed towards completion, verges filled and resoil ongoing. The Network Rail access has been substantially completed and reopened.
River Clyde - Formation trim is ongoing, verges filled and resoiling commenced.
Fullarton - With regard to earthworks this area has progressed little in the period (due to structural steelwork lay down), however, towards the end of June this will become a critical area as the steelwork erection, earthworks and drainage are all programmed ‘just in time' not to delay mainline pavement layers progressing.
Tie-In - During this period, bulk fill (including shoulder stitch ons) and improvement layer have commenced and substantial progress has been made.
Drainage - Good progress has been made throughout the section.
Roadworks - During the period mainline verge apparatus has progressed well.
Totals remaining are as follows:-
Motorway comms duct - 4530 metres, street lighting duct - 5500 metres, 649 environmental barrier posts
In relation to pavement the first layer CBGM has been laid from Southcroft Road to Quay Road and kerbing is progressing in that area.
Structures
Glasgow Road, Farmeloan Road & Fullarton Road - Deck finishes have commenced in advance of the approaching pavement train.
Cambuslang Road - The westbound deck was cast and subsequently temporary works supporting the beams removed. Parapets have commenced.
Auchenshuggle Underpass - Roof waterproofing/protection was carried out in the period.
Auchenshuggle Bridge - The substructure to both abutments is substantially complete with cladding ongoing. Preparation for steelwork erection is well advanced with the last beam sections arriving last week in May and large crane starting to be assembled week commencing 31 May for erection beginning on 12 June.
Most of the major project structures are now in place at both the West and East sections and preparations are now well under way for the work to build the remaining bridges required as part of the the 8 km road which links the existing M74 at Fullarton Road near Carmyle in the east to the M8 south of the Kingston Bridge.
Real progress has been made all along the route over the past month.
West Section
The M8/M74 Link Bridges are practically complete. Only the finishes such as surfacing, stainless steel parapet rail and expansion joints remain to be added to the eastbound bridge, with the joints of the pre-cast parapets already sealed. Waterproofing will commence in the near future, allowing the project team to use the bridge to access roadworks west of the bridge deck.
Backfilling of the abutments which will support the Westbound bridge has now been completed, while the parapet approaches are almost done. Waterproofing will be carried out at the same time as eastbound link viaduct.
Time lapse photography showing the successful launch of the westbound section of the Port Eglinton Viaduct can be found on the video section of the M74 site. Since these images were taken, work has continued to the support structures below the viaduct and these are now complete.
The launch of the eastbound section takes place later in the summer and the columns under the launch position are still being worked on.
All of the infill panels are complete up to pier 5 and reinforcement of the concrete deck is almost complete at piers 4 and 5. A total of 10 deck sections have been concreted and this concrete work will continue until December. The steel which will connect pier 5 to 7 is now all in place.
All but two of the 22 steel sections for the eastbound section of Port Eglinton Viaduct are on trestles and welding is progressing well. Half of the edge supports are in place.
All of the 10 steel beams for pier 10 to the east bridge abutment are now on site and will be lengthened in advance of their installation in June.
Brickwork cladding has re-commenced at the west abutment and is progressing well. Similar work to the east abutment will follow suit once the west abutment is completed.
Concreting of all 11 wall panels at retaining Walls 12 and 15, located between Pollokshaws Road and Strathbungo Road Link Underbridge, has been completed with only the gap panel remaining to be done. Parapet work is under way and pre-cast piling is programmed to follow in mid-May.
Work to construct the approach parapets at the Strathbungo Railway Underpass will commence once backfill to the structure has been completed.
Traffic continues to use the northbound half deck of the Cathcart Road Bridge, while piling for the second stage guide walls has re-commenced, with 10 of 54 piles now completed.
Beams have been ordered for Polmadie Road Underbridge and are expected to arrive in May. Beam support works are due to start imminently.
Major work is set to get under way to lift the beams into place at Rutherglen Railway Station Bridge. The majority of the substructure works have been completed and only the bearing shelves and plinths still remain to be done.
All 27 beams are now on site and the lift is expected to commence in mid May. The main steel works are expected to take three weeks, with another three weeks of secondary steel work to follow. Infill panels have been ordered and are expected to arrive in June.
Good progress has been made to the various Reco Retaining walls on the route. Wall 9 embankment at Kingston has been excavated, while the Polmadie eastbound off ramp retaining wall 18 is almost completed with just the wall coping (finishing slab) remaining.
Earthworks continue at Kingston, where 220,000m3 of the required 235,000m3 of material is now in place. Half of the bulk fill work behind the west abutment has been done, and pulverised fuel ash lightweight infill will be laid once this work has been completed.
Drainage work at Strathbungo will commence shortly, while only minor work on the road diversions remains at the Cathcart cut.
Mainline roadworks continue to progress well with 25,000 tonnes of cement bound granular material now in place along the route. Blacktop protection of this cement bound granular material has been applied to all sub-base areas.
A further layer of cement bound granular material is in the process of being laid at the Polmadie approaches, Cathcart Cut, the Strathbungo approach, Kingston embankment and the M74 / M8 Link Bridges approaches. Approximately 11,000 tonnes of material has to be laid for the West section of the project.
The on and off ramps at Polmadie are complete to the binder level - the layer of blacktop immediately preceding the final wearing course and around 35mm below the finished road level, while the Polmadie side road is 80% complete.
Reconstruction and re-alignment of the side roads at Kingston is under way. Drainage work is almost complete, while roadworks, street lighting and traffic light ducts are at various stages of completion at three of the nine streets. A total of 31 of the 59 road crossings have been completed. The majority of this work is being undertaken at night and on Sundays to minimise impact on daytime traffic flows.
East Section
Highlights for the East Section of the project during April have included the casting of the eastbound decks at Fullarton and Cambuslang and erecting the precast walkways at Auchenshuggle. Structural steelwork is now being delivered to the site.
Improving weather conditions have also allowed drainage and earthworks at the east end of the project to make significant progress.
Surcharge - the additional load to accelerate the settlement of existing soil - has been removed at Rutherglen Station, while bulk fill for the void between Farmeloan Bridge and the station is well advanced. Surcharging at Farmeloan Road will follow.
The surcharge has been removed at Cambuslang Road and verges have been formed. Sideslopes have been resoiled.
At the River Clyde, the void between Auchenshuggle Underpass and the west abutment has been filled with bulk fill material.
Fill has commenced at the west side of Fullarton Underbridge and the west side of Fullarton Roundabout following completion of the vibro stone columns, which are designed to aid consolidation of underlying soils.
Verges have been filled at Glasgow Road and the area has been capped, while trimming work is ongoing.
Gantry, Variable Message Sign and CCTV bases have been cast along the route, while motorway communication, street lighting and power supply ducts are in various stages of being installed. Work to realign the eastbound onslip at Fullarton and reconstruct the Fullarton Roundabout has also commenced.
Good progress is also being made to the various structures at the East end of the project. At Glasgow Road, the parapets and approach ground beams have been cast, while the approach ground beams have also been cast at Farmeloan Road
The eastbound deck at Cambuslang Road has been cast and 1000 cubic metres of concrete is set to be poured.
Following work to the roof and the wingwall cladding, the Auchenshuggle Underpass is now almost complete. The west side of the Auchenshuggle Bridge substructure is substantially complete, with the sandstone cladding to walkway level done and the precast walkways installed and cast.
On the east side, two upper wingwalls remain to be cast, although the sandstone cladding to walkway level is complete and installation of the precast walkway is well under way.
Seven sections of box girder have been delivered and are being welded on site.
Both Fullarton Bridge decks have been cast along with the parapet walls on the west structure.
Motorists travelling through Glasgow will have started to see some significant changes taking place to the city's road network as the M74 Completion project enters a crucial phase.
The project is rapidly approaching the second anniversary of work commencing and real progress continues to be made month by month.
The majority of the major structures are now in place and both the West and the East sections of the project have taken steps forward in the past month.
West Section
The M8/M74 Link bridges are almost finished - both eastbound and westbound. Only the finishes such as surfacing, stainless steel parapet rail and expansion joints remain to be added to the eastbound bridge, with the joints of the pre-cast parapets already sealed. Waterproofing is due to start imminently, after which the project team can use the bridge to access roadworks west of the bridge deck.
Backfilling of the abutments which will support the westbound bridge has continued throughout March, the parapet approaches are almost done and the reinforced earth wingwalls have been completed. Waterproofing work will be carried out at the same time as the eastbound link viaduct.
Following the successful launch of the westbound section of the Port Eglinton Viaduct last month, work has continued on the support structures below. All the columns under the launch position have been concreted up to piers 6 and 7, all temporary trestle foundation bases have been concreted and the intermediate support bases are complete.
Good progress has been made with the infill panels, with all of them complete up to pier 4 and work has started on the panels between piers 4 and 5. Reinforcement for the concrete deck is almost complete up to pier 3 and continues between piers 3 and 5 on both decks.
Four deck sections have now been concreted and this concrete work will continue until December. Meanwhile, work to erect the steel which will connect pier 5 to pier 7 started during the last weekend in March.
The second phase of the Port Eglinton launch - the eastbound section - takes place later in the summer and work to prepare for this is already under way. A total of 14 of the 22 steel sections are on trestles and welding work is continuing. To allow access to the deck in advance of the second launch, further traffic management in the area will be required and details will be outlined in due course.
Over half of the 10 steel beams for pier 10 to the east bridge abutment are now on site and will be lengthened in advance of their installation later in the summer. Brickwork cladding has re-commenced at the west abutment and the east abutment will follow suit once completed.
Steel reinforcement has been completed at 11 wall panels at retaining walls 12 and 15, located between Pollokshaws Road and Strathbungo Road Link Underbridge, with concreting completed at seven of them. Pre-cast piling is programmed to follow in mid-May.
Work to construct the approach parapets at the Strathbungo Road Link Underbridge will commence once backfill to the structure has been completed.
One structure which is already in use is the Cathcart Road Underbridge. Traffic has been diverted onto the northbound half deck following completion of the concreting, waterproofing and surfacing last month. Piling for the second stage guide walls is just getting under way and permanent piling will follow in due course.
Beams have been ordered for Polmadie Road Underbridge and are expected to arrive in May. The east bankseat at the bridge has been completed.
The next major engineering project will be the lifting of the beams at Rutherglen Railway Station Underbridge. To date, pier 3 columns have been completed, as has the supporting stem at pier 1, while work has started on the bridge columns. Excavation at pier 2 has been undertaken, while one base and stem have been cast with reinforcement work at the second base having been started.
All of the concreting at the west abutment front face has already been done and the next task is to do the same at the large wingwalls, which will be done over the next four weeks. A total of 22 of the 27 beams are now on site and it is hoped work to start lifting them into place will commence around May 10.
Significant progress has also been made to the various Reco retaining walls along the length of the route. The wall at the Polmadie westbound off ramp and the M8/M74 link viaduct wingwalls have all been completed, while wall 9 embankment at Kingston has been surcharged - that is, loaded with additional infil to promote rapid consolidation of the underlying soil - and the settlement is being monitored. The Polmadie eastbound off ramp retaining wall has almost been completed with just the wall coping - or finishing slab - remaining to be done.
Earthworks along the route are progressing well, with 210,000m3 of the required 235,000m3 of material in place at Kingston. The bulk fill work behind the west abutment has now started and the work to supplement this with pulverised fuel ash lightweight infill scheduled to begin next month.
Earthworks at Strathbungo are continuing on schedule, while only minor work on the road diversions remains at the Cathcart cut.
The good progress on structures is being more than matched with progress on roadworks along the route.
13,000 tonnes of cement bound granular material for the road sub base has been placed along the route and blacktop, up to within one layer of finished level, has been applied to all sub based areas.
Around 15,000 tonnes of cement bound granular material is due to be placed once sub base operations recommence on the second round of roadwork in March, and once that is done, only 11,000 tonnes for the west section of the project remain to be laid.
The on and off ramps at Polmadie have been completed to the binder level - the layer of blacktop immediately preceding the final wearing course, around 35mm below the finished road level -, while the Polmadie side road is 80% complete.
Reconstruction and re-alignment is under way at the side roads at Kingston, with work on drainage, roadworks, street lighting and traffic light ducts at various stages of completion at three of the nine roads. A lot of this work is being completed at night to minimise impact on daytime traffic flows.
Work is still to commence at Kinning St, Laidlaw St, Paterson St, West St, Wallace St and Paterson St North and most of this work will be undertaken on Sundays to reduce disruption to road traffic.
East Section
At the east end of the project, the structures at Glasgow Road and Farmeloan Road are substantially complete. Those at Cambuslang Road and Fullarton Roundabout have made significant moves towards completion during the month.
Earthworks between Southcroft Road and Glasgow Road and Farmeloan Road and Auchenshuggle are continuing, while surcharge is being removed between Glasgow Road and Rutherglen Station. Bulk fill work is progressing between Rutherglen Station and Farmeloan Road. Much of the drainage work at this end of the project has been completed.
Only parapet installation remains to be carried out at Glasgow Road Underbridge, while deck reinforcement at Cambuslang Road Underbridge continues.
The roof slab has been cast and backfilling has commenced at Auchenshuggle Underpass, while masonry work is progressing at Auchenshuggle Bridge. The decks have been cast at Fullarton Road west and east bridges.
Both the west and east sections of the M74 Completion project have seen significant progress during the month of February.
The launch of the main span of the westbound carriageway of Port Eglinton Viaduct is now finished. This major engineering feat involved pulling the bridge 166m into place over Eglinton Street and the West Coast Main Line. A repeat performance of this major civil engineering operation which will see the launch of the eastbound carriageway is scheduled to commence in May 2010.
Earthworks and roadworks are also progressing well.
West Section
M8/M74 Eastbound Link Bridge – The structure is substantially complete with only finishes, such as waterproofing, surfacing, the stainless steel parapet rail and expansion joints, outstanding. Pre-cast parapets have been erected on the whole of the structure. The approach parapet bases have been concreted.
M8/M74 Westbound Link Bridge – Backfilling has commenced to the abutments in conjunction with reinforced earth wingwalls, which are 70% complete. The stone column placement, which is designed to consolidate the ground between the structure and the existing M8 secondary carriageway, is now complete and preparation for the parapet approaches is under way.
Port Eglinton Viaduct – All substructure works are complete with the exception of the columns under the recently-vacated westbound carriageway launch position. All temporary trestle foundation bases are now concreted for the forthcoming eastbound carriageway launch, with the intermediate support bases completed where existing traffic management has allowed.
All beams are complete from the West Abutment to Pier 5. All the infill panels are now complete between the West Abutment and Pier 1 and are mostly complete to Spans 2 and 3. The steel reinforcement has almost been completed to Span 1 and continues over Span 2 to both decks. The first concrete - to the centre of Span 1 – has already been poured.
Twelve of the 22 steel sections for the second phase of the launch – the eastbound carriageway - are now on trestles and welding has started. A further four beams have been delivered to the site.
Steel beams are being lengthened in the Network Rail area of land accessible off Salkeld Street and will be erected once the final pieces of work on the westbound carriageway have been completed – scheduled mid-March. Steel beams for the stretch from Pier 10 to the East Abutment are ready for delivery and will start to arrive at the site shortly.
Retaining Walls 12 and 15 – All of the bases have been concreted. Scaffolding for walls eight of 12 has been erected, steel reinforcement is under way to four of the 12 walls and wall forms – the moulds into which the concrete is poured to form the walls - are being assembled.
Strathbungo Railway Underpass – Approach parapets will commence following backfill to the structure.
Cathcart Road Bridge – Deck stage one is now concreted and permanent service diversions are almost complete. The deck has been waterproofed and the sand carpet - a thin protective bituminous layer – has been laid. A steel parapet has been erected to the west cope, which will allow an early start to stage two piling, which is currently planned for the end of March.
Network Rail Relay Station Access Road – Can now be used as diverted access to allow work on the westbound on-ramp to commence.
Polmadie Road Bridge – The beams have been ordered and are due to arrive in April. The east bank seat excavation has been blinded with concrete ready for the steel reinforcement, which will take place following the completion of Wall 18.
Reco (Reinforced Earth Company) Retaining walls – Wall 17 (Polmadie West) is complete. Wall 9 (Kingston) is also surcharged with settlement being monitored. Walls 6 and 4 (M8/M74 Westbound Link Bridge wingwalls) are under way and are around 70% complete. Wall 18 (Polmadie East) has been erected, although the copes remain to be completed.
Earthworks and roadworks – Earthworks are ongoing at Kingston, with 205,000m3 of the required 235,000m3 in place. The bulk fill behind the West Abutment is planned to start after crane is finished work at the west end of the Port Eglinton Viaduct deck.
Around half of the earthworks at Strathbungo are completed. Only minor works remain for the road diversion at Cathcart.
Mainline roadworks have progressed well with 13,000 tonnes of cement bound granular material in place. Blacktop protection of this material has been completed following the cold winter temperatures. On and off ramps at Polmadie are now being surfaced.
Side roads at Kingston – Reconstruction and re-alignment is under way. At three of the nine streets, around 70% of drainage work has been completed, 30% of roadworks and around half of the street lighting and traffic light ducts have also been finished. Fourteen of the 59 road crossings are complete.
Streets still to be started are Kinning St, Laidlaw St, Paterson St, West St, Wallace St and Paterson St North. Work will be undertaken 15 Sundays in a row in order to minimise the impact on road traffic.
East Section
Earthworks - Since last month, the improvement layer has been substantially completed to the west of Glasgow Road. At the soil treatment centre, 8000m3 of material from Rutherglen Station structures excavations await transfer into the embankment between Rutherglen Station and Farmeloan Road. A total of 13000m3 will have been incorporated into the works from this structure following geotechnical and/or chemical treatment.
The embankment remains under surcharge to the east of Glasgow Road, which will be the last to be surcharged.
Beyond Farmeloan Road, surcharge is being removed and transferred to both Auchenshuggle and Rutherglen to be used as backfill, allowing mainline drainage to progress. Towards Cambuslang Road, the Network Rail access track and westbound merge sliproad have been excavated.
The surcharge is being removed and the improvement layer placed in advance of mainline drainage commencing beyond Cambuslang Road. Near the River Clyde to the west of Auchenshuggle Bridge, grouting has been undertaken to successfully stem artesian water.
Drainage – No major work other than the grouting of the existing, now redundant, culverts in the Fullarton area commencing.
Roadworks – Work to install gantry and Variable Message Signs bases has commenced.
Structures - 170 precast beams have been placed over Cambuslang Road and the west side of Fullarton Roundabout.
At Glasgow Road, the bridge decks have been cast and parapet construction work is under way. The beams are in place at Cambuslang and deck construction work has started.
Work on the masonry facing the abutments at Auchenshuggle Bridge has commenced, while the East bridge at Fullarton is awaiting beams, which will be delivered by mid March. The deck of the West bridge will be cast shortly.
Rutherglen Railway Station bridge work moves on apace. The stem of Pier 3 has been cast to both bases and scaffolding has gone up on the columns above. Two bases and one of the two stems have been cast at Pier 1, while piling work at Pier 2 has to commence, although steel reinforcement to one half has started. The adjacent retaining wall has seen all four wall stems concreted and is awaiting parapets.
West Section
M8/M74 Eastbound Link Bridge - The structure is substantially complete, with only the finishes remaining. Pre-cast parapets have been erected to 80% of the structure.
M8/M74 Westbound Link Bridge - The bridge is substantially complete and backfilling to the abutments continues, as does work to the reinforced earth wing walls, which retain soil behind the abutment. Work to these is around 70% complete. While lanes of the M8 were temporarily closed, enabling works for stone columns to support the retaining walls have taken place.
Port Eglinton Viaduct - All substructure works have been completed, with the exception of columns under the viaduct launch position. All temporary trestle bases are now concreted and intermediate support bases are complete. Pre-cast piling has completed behind the west abutment.
All beams for the work to complete the deck beams from west abutment to pier 5 have been erected. Infill panels to support the reinforced concrete deck have now commenced to span 1.
All steel sections for the first stage of the bridge launch over the West Coast Main Line railway and Eglinton Street have been completed and the launch nose is connected. The deck and parapets for the section over the railway lines are concreted and the launch will commence on Saturday 30th January.
Beams for the second phase of the bridge launch are on site and are being prepared for erection following the completion of the first stage.
Retaining Walls 12 and 15 - five of the six bases have been concreted. The sixth base will follow pre-cast piling between the walls.
Strathbungo Railway Underpass - The bridge is substantially complete and construction of approach parapets will commence once backfill to the structure has been completed.
Cathcart Road Bridge - The first stage of the deck (the west half) is now concreted and permanent service diversions are under way. Traffic is expected to switch back on to the line of the existing road, using the west half of the new bridge, in March after completion of the ongoing service diversions. This could allow a start to the second stage piling work, which is currently planned for the end of March.
Network Rail access road - The road has been altered to allow use as a diverted access, which in turn allows work on the westbound on-ramp to start.
Polmadie Road Bridge - Columns have been concreted to the centre pier. Construction of the east bank seat will follow after work on wall 18 is complete. Beams are ordered for March 2010.
Retaining walls - Wall 17 (Polmadie west) is complete and Wall 9 (Kingston) has been surcharged, whereby surcharge is put in place temporarily to speed up the settlement of the ground underlying the embankment, and the settlement is being monitored. Work at walls 6 and 4 (M74/M8 westbound link bridge wing walls) is under way and is around 70% complete. The erection of Wall 18 (Polmadie east) is about 50% completed.
Earthworks and Roadworks - Earthworks are ongoing at Kingston with 205,000m3 of the 210,000m3 required in place. Surcharge removal at Polmadie East has been transferred to Scotland St.
Earthworks at Strathbungo are 50% complete and 73,500m3 of fill has been transported to the east section of the route.
The only earthworks remaining at Cathcart involve the excavation around and below the new overbridge. Roadworks and associated drainage are well advanced in the area.
Mainline roadworks have progressed well with 60,000m2 of surfacing material now in place, 90% of which is now covered with blacktop. Drainage works at the on and off ramps at Polmadie are complete and kerbing should begin imminently.
East Section
Glasgow Road Bridge - Following completion of beam erection, deck construction continues, with reinforcement and edge formwork ongoing.
Rutherglen Railway Station Bridge - All piling is now completed and the stem at pier 3 has been cast. At pier 1, one base has been cast and the fitting of reinforcement stem bars is under way. Concreting of the second base at pier 1 is due to commence imminently. Piling work at pier 2 is ongoing and construction of the west abutment base is under way. The adjacent retaining wall 23 is substantially complete.
Farmeloan Road Bridge - The bridge is substantially complete.
Cambuslang Road Bridge - Placing of precast beams has commenced.
Auchenshuggle (River Clyde Crossing) Bridge - On the west side, the gallery wall is under way, upper wing walls have commenced and backfill is continuing. Work is well advanced on the east abutment.
Fullarton Roundabout Bridges - The abutments for both the east and west bridges are substantially complete. Beam deliveries for the west bridge will take place in mid-February, with the east bridge beams following in March.
Earthworks - Work continues at Glasgow Road as weather allows.
The Rutherglen Station area remains under surcharge and work on the small reinforced earth retaining wall has been completed.
At the River Clyde, the Scottish Power access track has been excavated, backfilled and capped and the removal of surcharge has commence.
Work on the retaining wall at Fullarton Road has been completed.
Drainage - Approximately 70% of new drainage has been laid.
Roadworks - Work on the existing M74 to the east of Fullarton Road has progressed to the stage where the surface course is now complete and has been relined.
West Section
M8/M74 Eastbound Link Bridge - With the sub-structure complete, work has been progressing on the pre-cast parapets. Fitted as safety barriers to the edge of the bridge, the parapets have been erected to 30% of the structure.
M74/M8 Westbound Link Bridge - Backfilling to the abutments of the bridge is continuing and the reinforced earth wing walls which retain soil behind the abutment are 70% complete.
Port Eglinton Viaduct - The erection of the bridge beams is progressing well with all twelve of the beams required for stage three of the structure programme erected, completing the deck beams from the west abutment to pier 5. The erection of permanent formwork panels, which act as moulds for the concrete forming the structure, is now underway at the first span.
All 22 steel sections required for the first stage of the bridge launch are now in position and the launch nose is connected; this is a temporary girder attached to the front of the sections to help guide them into place during the launch.
Formwork panels have been completed to the launch section, the concrete deck pour has taken place and parapet construction is ongoing. Eight of the 22 steel sections of the second phase of the bridge launch are now on site.
Retaining Walls 12 and 15 - Piling is now complete and the fitting of steel reinforcement bars to the bases has commenced with two of the ten bases concreted.
Strathbungo Railway Underpass
- Work will commence on the approach parapets once backfill has been completed.Cathcart Road Overbridge - The first stage of the deck is now concreted and permanent service diversions are underway which will be followed by the switch of traffic in the first quarter of 2010.
Polmadie Road Underbridge - Piling to the centre pier has been completed and the two bases concreted.
Rutherglen Station Underbridge - At the west abutment piling is now complete and excavation is underway. The fitting of steel reinforcement bars to pier 3 is underway with the base concreted and the wall and column now in progress.
At pier 1 piling is complete and one of the two bases has been concreted while piling work is ongoing at pier 2 with sheet piling now complete.
Reco Retaining Walls - At wall 17 (Polmadie), secondary settlement is now complete with cope, which caps the top of the wall, in place. Wall 9 (Kingston) is surcharged, whereby surcharge is put in place temporarily to speed up the settlement of the ground underlying the embankment, with settlement being monitored. Walls 6 (the wing wall of the M8/M74 Westbound Link Bridge) is 70% complete while at wall 18 (Polmadie) surcharge is now cleared and wall erection underway.
Earthworks and Roadworks - Earthworks are ongoing at Kingston with 205,000m3 of the 210,000m3 required in place. Earthworks at Strathbungo are 50% complete and 73,500m3 of fill has been transported to the east section of the route.
Mainline roadworks have progressed well with 60,000m2 of surfacing material now placed, 90% of which is now covered with blacktop surfacing.
EAST SECTION
Glasgow Road Underbridge - Deck construction is progressing at Glasgow Road with two of the bridge diaphragms now cast and temporary works ongoing.
Cambuslang Road Underbridge - Temporary works supports have been erected in preparation for the beam erection in early January.
Auchenshuggle Bridge - On the west side of the river, the upper wing walls, which retain the embankment fill behind the abutment, and gallery floor of the structure have been cast. On the east the abutment and wing walls are cast to bearing shelf level.
Fullarton Roundabout - The substructures of both bridges at the roundabout are complete and awaiting beam erection in February.
Earthworks - At Glasgow Road backfilling has commenced following the completion of the Westburn culvert.
The Rutherglen Station area remains under surcharge and work has commenced on the small reinforced earth retaining wall progressing to the coping stage which caps the top of the wall.
At the River Clyde the Scottish Power access track has been excavated, backfilled and capped while at Fullarton Road work on retaining wall 29 has progressed to cope level.
Roadworks - During the period works at the existing M74 progressed through two further traffic phases and are on programme for substantial completion by the new year. Verge slabbing and other works will be carried out in January.
West Section
M74/M8 Eastbound Link Bridge – With the substructure now complete and the planks for the bridge decking installed, all eight concrete deck pours have now taken place. The production of the pre-cast parapets, which will be fitted as safety barriers on the edge of the bridge, is 50% complete.
M74/M8 Westbound Link Bridge – Backfilling to the abutments of the bridge is continuing and the reinforced earth wing walls which retain soil behind the abutment are 70% complete.
Port Eglinton Viaduct – All substructure works are complete with the exception of the columns under the launch position. All temporary trestle bases, which provide temporary support to the structure during construction, are now concreted with intermediate support bases complete where traffic management allows. Piling behind the west abutment is also finished.
The erection of the bridge beams is progressing well with ten of the twelve beams required for stage three of the structure programme erected, completing the deck beams from the west abutment to pier 5. Permanent formwork panels, which act as moulds for the concrete forming the structure, are now ready and will be erected in next period.
Eighteen of the of 22 steel sections required for the first stage of the bridge launch are now in position and formwork panels have started to be placed. Four of the 22 steel sections of the second phase of the bridge launch are now on site.
Retaining Walls 12 and 15 – Piling is underway with 102 of 108 piles required in place. The fitting of steel reinforcement bars to the bases has commenced.
Strathbungo Railway Underpass –The bridge parapets are now complete and work will commence on the approach parapets once backfill has been completed.
Cathcart Road Overbridge – The first stage of the deck is now concreted and permanent service diversions are underway which will be followed by the switch of traffic in the first quarter of next year.
Polmadie Road Underbridge – Piling to the centre pier has restarted and is now nearing completion. Beams are ordered for March 2010 and the west bank seat is concreted with the east to follow.
Rutherglen Station Underbridge – At the west abutment piling is now complete and excavation is underway. The fitting of steel reinforcement bars to pier 3 is underway while at pier 1 piling is progressing well with fourteen of twenty piles complete. The construction of the east abutment is advancing well.
Reco Retaining Walls – At wall 17 (Polmadie), secondary settlement is now complete with cope, which caps the top of the wall, in place. Wall 9 (Kingston) is surcharged, whereby surcharge is put in place temporarily to speed up the settlement of fill materials, with settlement being monitored. Walls 6 (the wing wall of the M8/M74 Westbound Link Bridge) is 70% complete while at wall 18 (Polmadie) surcharge is now cleared and wall erection underway.
Earthworks and Roadworks – Earthworks are ongoing at Kingston with 205,000m3 of the 210,000m3 required in place.
Mainline roadworks have progressed well with 60,000m2 of surfacing material now placed, 70% of which is now covered with blacktop surfacing.
Major utility diversions for Polmadie Road Underbridge are complete with traffic now flowing on diversion to allow access to centre pier.
East Section
Glasgow Road Underbridge – The beam erection is now complete and the construction of the deck is ongoing.
Farmeloan Road Underbridge - The revetment blinding, which helps disguise the walls of the embankments, was cast to the slopes under the bridge.
Cambuslang Road Underbridge - The centre piers have been cast and preparation is now underway for the beam erection in early January.
Auchenshuggle Underpass - The structure has been excavated, blinded and the base cast during the period.
Auchenshuggle Bridge - On the west side the abutment is currently sitting at bearing shelf level with backfilling now complete. The next key milestone will be delivery and erection of the precast walkway. On the east side two of the three abutment walls have been cast.
Fullarton Roundabout - At the roundabout the two main structures have progressed to the stage where the west bridge substructure is complete and the east has two walls outstanding. Work is scheduled for completion in advance of the beam deliveries in early 2010.
Earthworks - Overall around 100,000m3 of material remains to be placed in structures approaches, between Farmeloan and Rutherglen structures and the centre of Fullarton Roundabout.
At Glasgow Road the westbound carriageway is substantially complete and improvement layer placed. Progress on the eastbound carriageway will continue upon completion of the Westburn culvert manhole and the removal of the soil treatment centre.
The Rutherglen Station area is presently under surcharge and work has commenced on the small reinforced earth retaining wall adjacent to old Quay Road.
Some surcharge has now been removed from Cambulslang Road and placed as fill behind west abutment of Auchenshuggle Bridge. Works elsewhere have included completing the excavation and capping of the westbound merge slip road from Cambuslang Road. In addition the new access road to the rail depot has progressed.
At the River Clyde the Scottish Power access track commenced this month while at Fullarton Road work got underway on retaining wall 29.
Drainage – To date 78% of pre-earthworks pipes have been laid and 39% of mainline pipes are in place.
Pre-earthworks drainage at Glasgow Road is well advanced with only the area at the soil treatments centre to be completed. Mainline drainage also commenced during the month.
The works at Quay Road North have progressed well with only the connection to the SUDS pond (the Sustainable Urban Drainage System deals with surface water runoff in an environmentally friendly way) and the final pipe into the Clyde outstanding.
Mainline drainage commenced at Fullarton Road during the period and various nightshifts were deployed to construct culverts 12, 15 and 16.
Roadworks – Roadworks have been focused on the existing M74 where reconstruction of the westbound diverge progressed to the extent where traffic was switched. Work is now ongoing in the central reserve area. In addition the utility diversions at Fullarton Roundabout have commenced.
West Section
M8/M74 Eastbound Link Bridge – With the substructure now complete and the planks for the bridge decking installed, five of the eight required deck pours have taken place. The production of the pre-cast parapets, which will be fitted as safety barriers on the edge of the bridge, is 50% complete.
M8/M74 Westbound Link Bridge – Backfilling, where excavations are refilled, has commenced to the abutments of the bridge. Reinforced earth wing walls which retain soil behind the abutment are 40% complete.
Port Eglinton Viaduct – All substructure works are complete with the exception of the columns under the launch position. All temporary trestle bases, which provide temporary support to the structure during construction, are now concreted with intermediate support bases complete where traffic management allows. Piling behind the West abutment is also finished.
Eighteen steel beams have been erected from the west abutment to pier 3 and work is almost complete to these beams to allow access to deck operations. Permanent formwork is ready to start. Twelve steel sections for the first stage of the bridge launch are now in position being welded at trestle height.
Retaining Walls 12 and 15 – Piling is underway with 71 of 108 piles required in place. The fitting of steel reinforcement bars should commence to the bases shortly.
Strathbungo Railway Underpass – The deck and wing walls are now complete with work on the parapets underway.
Cathcart Road Bridge – Soffit support which supports the underside of the structure is now complete and the reinforcement of the first stage of the deck with steel bars is around 30% complete. The deck pour is currently planned for early November which will allow permanent service diversions to progress.
Cambuslang Road Underbridge – Save the centre pier and revetment blinding this structure has progressed to the same stage as Glasgow Road Underbridge. During October the centre pier base and three of the nine columns have been cast.
Auchenshuggle Bridge - On the west side the abutment is currently sitting at bearing shelf level with backfilling underway. On the east the base is cast and abutment wall reinforcement is ongoing.Surcharge is still in place from Farmeloan Bridge to the approach to Cambuslang Road and excavation for the westbound merge slip road has been carried out.
At the River Clyde the main focus has been on removing and treating a pocket of paper pulp. The import of fill material will recommence following the beam erection at Cambuslang Road Underbridge and further work to the Corus access track.
Drainage – At Quay Road North drainage works are progressing well as has mainline drainage at the River Clyde. Work on culverts 12,16 and 16 at Fullarton Road has commenced, running parallel to the main embankment through the Clyde Investment Park.
Roadworks - During October the verge widenings on the existing M74 have progressed to the stage where the eastbound carriageway verge, slip road and lanes one and two have been reconstructed and opened to traffic. Work now progressing towards the central reserve. On the westbound carriageway verge surfacing is underway following demolition of the existing gantry.
West Section
M8/M74 Westbound Link Bridge – Concreting of the parapets and concrete finishing work is complete and backfilling, where material is used to refill excavations, has commenced to the abutments. Preparation works are underway for the wingwalls.
Port Eglinton Viaduct – Work on the piers is progressing well with 1800mm diameter columns in place at piers 1 to 5 and 2400mm diameter columns complete to piers 9, 10 and 11. The east abutment bearing shelf has been concreted while behind the west abutment 340 of the 460 piles required have been driven into place. Temporary Trestle 2 piles, which offer temporary support to the structure during construction, have been cut down ready for pilecap construction. Steel bridge beams are currently being erected from pier 3 to the west abutment.
Retaining Walls 12 and 15 – Piling is underway with 44 of the 108 required piles completed.
Strathbungo Railway Underpass – The underpass remains three months ahead of programme; the deck now concreted with the wingwalls to follow.
Cathcart Road Bridge – Concrete has now been placed to the first stage of both abutments. Minor excavation is now underway as is the installation of low level soffit support which supports the underside of the structure.
Polmadie Road Bridge – Piling at the east abutment is over 50% complete with the west abutment to follow. Columns are complete to piers 1 and 3.
Rutherglen Railway Station Bridge – Piling work is progressing with the east abutment and adjacent retaining wall complete, the west abutment well underway and pier 3 nearing completion. The level crossing to access pier 1 and 2 is now fully complete. There will be two weeks of piling platform and sheet pile installation, which creates a retaining wall to hold back soil, before the commencement of piling at pier 1 and 2.
Reco Retaining walls – At Polmadie the panels at wall 17 have been erected with monitoring of settlement ongoing. Surcharge, which is put in place temporarily to speed up the settlement of fill materials, is in place at wall 18 with settlement ongoing; erection of the wall erection is now planned for October following piling adjacent at Polmadie East.
At Kingston walls 1 and 2 are complete with 4 and 6 to follow. Surcharge is in place at wall 9 and settlement is being monitored.
Earthworks and Roadworks – Earthworks are ongoing at Kingston with 175,000m3 of the 210,000m3 of materials required in place. The ‘slurry wall’, which is a reinforced-concrete wall used in areas of soft, wet earth is complete
At Polmadie East earthworks are continuing with surcharge being removed and transferred to Scotland St.
Earthworks at Strathbungo are 50% complete.
Mainline roadworks are ongoing with 50,000m2 of formation fill placed and drainage progressing well. Surfacing is underway at Polamadie East.
Major utility diversions for Polmadie Road Underbridge are now underway with associated permanent roadworks being carried out.
East Section
Glasgow Road Underbridge - Substructure works are complete at Glasgow Road. Temporary works will commence early October with delivery of the beams, which will form the main deck structure, due for delivery by early November.
Cambuslang Road Underbridge – The majority of the substructure is complete with only work on the central pier remaining. At the central pier piling is complete and the central base has been excavated and blinded with reinforcement underway.
Auchenshuggle Bridge - At the west abutment all walls up to the bearing shelf level are complete, whilst at the east abutment the base has now been cast.
Fullarton Underpasses – At the west underpass both bases are cast and work on the east abutment wall is progressing towards the first concrete pour.
At the east underpass again both bases are cast with wall reinforced underway to the west abutment.
Earthworks - To date 619,000m3 of fill material has been imported with 153,000 m3 remaining.
At Rutherglen Station surcharge is now in place with the exception of the bridge approach and wall 22.
The importing of fill and surcharge is complete at Cambuslang Road with bulk excavation to the westbound merge slip and Network Rail access track commenced while at the River Clyde the import of clay material from the Hoover factory is ongoing.
Drainage - At Rutherlgen Station drainage work is progressing at Quay Road North including the SUDS pond – the Sustainable Urban Drainage System deals with surface water runoff in an environmentally friendly way.
At the River Clyde pre-earthworks, mainline and SUDS ponds are all progressing well and further culvert manhole covers have been put in place.
Pre-earthworks drainage is now complete at Cambuslang Road and Fullarton Road where available.
In the M74 widening area at Carmyle Road the pre-earthworks and mainline drainage have been carried out and gullies installed.
West Section
M74/M8 Eastbound Link Bridge – The sub-structure is now complete and all steelwork has been erected and bearings grouted. The placement of planks which will form the bridge decking is underway over areas not affecting motorway traffic with traffic management in place to complete the process. The commencement of deck reinforcement is imminent.
M74/M8 Westbound Link Bridge – The bridge deck is now cast with works ongoing on the parapets; concreting is almost complete. Backfilling, where the excavations are refilled, has now commenced to abutments and preparatory works are underway for the wingwalls which retain the soil behind the abutments.
Port Eglinton Viaduct – Piling is now complete to all areas and at the West abutment reinforced concrete works are also finished. At piers 1,2,3,4 and 5 the 1800mm diameter columns are in place while the 2400mm diameter columns are complete to piers 9, 10 and 11. Temporary trestle piles have been cut down ready for the construction of pilecaps.
Strathbungo Railway Underpass – Work has progressed ahead of schedule with the underpass walls complete and the installation of soffit support, which supports the underside of the structure underway. Deck rebar, which uses concrete strengthening steel bars to support the bridge deck, will be underway early September.
Cathcart Road Bridge – The first phase of piling is now complete with the second phase planned for 2010. The pile heads have been broken down, whereby the piles are trimmed to the required level, and blinding placed to the north abutment.
Polmadie Road Bridge – All drilling and grouting in the west section is now complete.
Rutherglen Railway Station Bridge – Piling to the east abutment is complete and piling to the adjacent retaining wall 23 is significantly underway. Piling to the west abutment will commence in early September. Test piling has been approved for piers 1, 2 and 3 with work on pier 3 beginning during this month; this is likely to take around four weeks to complete.
Mineworkings and Grouting – All drilling and grouting in the west section is now complete.
Earthworks and Roadworks – Earthworks are ongoing at Kingston with 165,000m3 of the required 230,000m3 of fill in place. The slurry wall, which reinforces the concrete wall, is complete.
Precast concrete driven piling commenced behind the west abutment of the Port Eglinton Viaduct on 24 August and is anticipated to be ongoing for five weeks.
Earthworks are continuing at Polmadie. The west embankment is now complete and the required 67,000m3 of fill and surcharge in place. The east section embankment is also complete with filling to the east abutment of Polmadie Road Underbridge ongoing.
Earthworks at Strathbungo are 50% complete.
44,000m3 of the 71,500m3 of fill required has been transported to the east section.
30,000m2 of formation fill has been placed as part of the mainline roadworks and drainage works are progressing well. Major utility diversions and permanent roadworks for the Port Eglinton Viaduct are underway.
East Section
Glasgow Road Underbridge - The substructure is nearing completion with the beam erection due to take place in October.
Cambuslang Road Underbridge - Progress is well underway with only the centre pier and sections of the east abutment outstanding and beam erection scheduled for later this year.
Auchenshuggle Bridge – On the west abutment, the base and first of three walls has been cast whilst on the east side the base has been blinded, the piles cropped to required level and reinforcement work has commenced.
Fullarton Underpasses – At the west underpass both abutment bases have been cast and backfilled. On the east side both abutments have been excavated, blinded and the piles cropped.
Earthworks – Wet weather has reduced the volume of fill delivered each week to 20,000m3. To date, 574,000m3 of the required 766,000m3 of fill has been imported.
Drainage - At Cambuslang Road drainage works are progressing well and pre-earthworks drainage on the northern boundary is nearing completion.
Works from Cambuslang Road to the Clyde are progressing toward completion.
At Fullarton Road Pre-earthworks drainage has commenced and is nearing completion along the northern boundary.
M74/M8 Eastbound Link Bridge – The substructure of the bridge is now complete and all steelwork is on site with final assembly well underway. The erection of beams is progressing well with the first of eight huge beams lifted into place on 30 July using Europe’s largest mobile crane.
M74/M8 Westbound Link Bridge – The deck and diaphragms, which provide support to the structure, have now been cast while work on the parapets is ongoing. All beams in place.
Port Eglinton Viaduct – Piling is now complete to all areas and the construction of the east and west abutments is well underway. At pier 2 the pilecap has been cast and five of the six columns required are complete. The 1800mm diameter columns are complete to piers 1, 3, 4, and 5 and at piers 10 and 11 the 2400mm diameter columns are in place.
Strathbungo Railway Underpass – Work on the underpass is progressing well with four of the six required concrete walls poured.
Cathcart Road Bridge – Piling to phase one is complete; phase two will begin in 2010.
Polmadie Road Bridge – Gas service diversions are underway and columns are complete to piers 1 and 3. Anticipated duration of gas diversion is 8 weeks. Thereafter central pier and abutment piling can commence.
Rutherglen Railway Station Bridge – Piling to the east abutment of the bridge is complete and has now commenced for the adjacent retaining wall. Precast piling is also underway on the embankment and will progress to the west abutment.
Band Drains – All band drains in the west section are now complete.
Mineworkings and Grouting – 89% of the drilling work and 86% of grouting is complete; final completion is scheduled for August.
Earthworks – Earthworks are ongoing at Kingston with 154,000 m3 of the required 230,000m3 of material in place. The east section embankment 95% of the earthworks are done and at Strathbungo they are 50% complete.
Glasgow Road Underbridge - All piling is complete with progress on the east and west abutments ongoing in advance of the beam erection planned for November.
Farmeloan Road Underbridge – The underbridge is substantially complete with only a few components such as concrete finishing and deck waterproofing outstanding.
Cambuslang Road Underbridge - The west abutment base and bearing shelf are cast, as are the east and west piers while the east abutment is now ready for steelfixing. The beams for the west span have been delivered ready for erection.
Auchenshuggle Bridge – Piling is now complete with work progressing well on both the east and west abutments. The latter is now excavated with steelfixing work in progress while excavation is now complete on the east abutment.
Fullarton Underpasses – At the west bridge piling is now complete with steelfixing work ongoing on the west abutment and excavation underway for the east abutment.
At the east bridge piling work is progressing well with the west abutment complete and piling to the east abutment recently commenced.
Earthworks – Earthworks on the west section are progressing with 22,000m3 of fill materials being delivered on average each week. Approximately two thirds of the 766,000m3 of fill materials required is now in place.
Culverts - Of the culverts to be constructed, 363 metres of the 703 metres required have been laid with the current focus on Westburn Culvert.
Mineworkings and Grouting - Grouting is progressing well and earthworks have now commenced with work now 84% complete; final completion is due in August 2009.
M74/M8 Eastbound Viaduct - The sub-structure work is now complete. The assembly of beams at Cook Street and Gloucester Street is in progress and crane platforms are now prepared for the beam erection which is due to take place late July.
M74/M8 Westbound Link Bridge – Again the sub-structure work has been completed with reinforced concrete beams in place across all three spans and the deck pour complete.
Port Eglinton Viaduct – Piling is now completed to all areas with around 85% of the reinforced concrete required in place on pilecaps and abutment. The erection of steelwork is due to begin in August 2009.
Strathbungo Railway Underpass – Construction of the underpass is three months ahead of schedule; the full base has been concreted and the wall construction is well underway.
Cathcart Road Overbridge – Phase one of piling is 90% complete with phase two due in 2010.
Polmadie Road Underbridge – All columns completed with service diversions underway and the commencement of abutment piling imminent.
Rutherglen Station Underbridge – Piling of the east abutment is complete and has commenced for adjacent retaining wall.
Reco Retaining walls – The construction of retaining walls for the embankments is making progress with walls 1, 2 (Kingston), 10 (Scotland St) and 17( Polmadie) underway.
Band Drains – All band drains in the West section of the route are complete.
Earthworks and Roadworks – Earthworks are ongoing at Kingston with 145,000m3 of a total of 230,000m3 of material placed. At Polmadie all material is in place while at Strathbungo earthworks are 50% complete.
Further sources of reusable material have been identified with the potential of further reducing the need to import fill and thereby minimise the environmental impacts of transporting materials from elsewhere.
Earthworks - To date, 515,000m3 of 766,000m3 has been placed; the remaining fill shall be completed in October of this year.
Quay Road – The import of fill material is ongoing.
Cambuslang Road – The import of fill material is substantially complete with only the Network Rail access track and westbound merge slip road awaiting progression.
River Clyde – Paper pulp remediation, whereby paper pulp present in the existing soil is treated to ensure a solid foundation for structures, is now complete and mine seam consolidation to the eastern embankment is nearing completion. Works will commence on the western embankment approaching Cambuslang Road once band drains are complete in late July with fill material being imported on an ongoing basis until September 2009.
Fullarton Road – Mine seam consolidation in this area is now finished and bulk import is ongoing. Vibro stone columns, a technique used to construct columns in fill material, have been installed on the western approach to Fullarton Roundabout.
Pre-Earthworks Drainage – Good progress has been made throughout the section.
The culverts at Eastfield, Battleburn and Scion are complete.
Glasgow Road Underbridge - Piling work is complete; reinforcement and formwork to the west abutment are ongoing with concrete works having commenced at the end of June.
Farmeloan Road Underbridge - This structure is substantially complete with work progressing on the parapets; the removal of temporary works and waterproofing of the deck will follow.
Cambuslang Road Underbridge - To date the west abutment base and bearing shelf, the west pier base and columns and the east pier base have all been cast. Work on the east columns is ongoing and piling to the east abutment is now underway. The delivery of the bridge beams has begun and they will be stored until the other columns have been completed.
Auchenshuggle Bridge – Piling work is now complete and excavation works are underway. The west abutment is progressing towards a major base pour at the end of July.
Fullarton Underpasses – Piling for both structures is 75% complete; steelfixing
West Section (Kingston Junction to Polmadie)
Mineworkings and Grouting
Earthworks are due to be released mid June. Work is 63% complete with final completion anticipated in August 2009.
M8/M74 Eastbound Link Bridge
Sub-structure work on the link bridge is now substantially complete. Crane platforms are now prepared for beam erection with beam assembly due in June and beam erection scheduled to commence in July.
M8/M74 Westbound Link Bridge
Again sub-structure work is now substantially complete; temporary beam support is underway. Pre-cast beams are planned for 8th June.
Port Eglinton Viaduct
Piling is now complete in all areas with the exception of piers 2 and 9. Piling for the temporary support trestle on the junction of Eglinton Street and Kilbirnie Street is complete with piling on pier 2 underway in June. Temporary sheet piling, whereby a retaining wall is created by driving sheets of materials into the ground, is completed at pier 3 with excavation already started. Excavation work on the East abutment of the bridge has also commenced.
Structural concrete work has commenced with pier 11, 10, 8, 7, 6, 5, 4 and 1 with pile-caps poured – these are the structures which tie the groups of individual pile columns to provide a solid support for the structure above. The West abutment base is complete with one of the six wall pours required completed. Columns are also progressing well and are complete for piers 1,4,5,10 and 11.
Strathbungo Railway Underpass
Progress on the railway underpass is going well and is currently three months ahead of schedule.
Cathcart Road Bridge
The first phase of piling is underway with phase two following in 2010.
Network Rail Access Road
Earthworks have started with 50% of road alignment shaped.
Polmadie Road Bridge
Piling has been completed for pier 1 and 3 with work commencing on pier 2 mid August. The base of pier 1 is concreted and resources are now on pier 3.
Rutherglen Railway Station Bridge
The test pile has been completed successfully for the planned Large Diameter Auger (LDA) piles. Construction of the piling platform, the working platform from which piling is installed, is underway.
Band Drains
All band drains in the West Section are now complete.
Earthworks and Roadworks
Earthworks are ongoing at Kingston with 137,000 cubic metres of a total of 230,000 cubic metres of material placed. They have also recommenced at Polmadie with lime modified improvements to 29,000 cubic metres of 67,000 cubic metres of material complete. At the East section 48,000 cubic metres of 65,000 cubic metres have been placed and earthworks at Strathbungo are 50% complete.
Structural Steelwork
Steel beam fabrication and delivery is on course with the first beams currently in storage. These beams will be transferred for erection at West Street (Port Eglinton Viaduct) in early July.
The Paisley Road off-ramp will be temporarily closed from midnight on 27 June to midnight on 3 July in preparation for beam erection for the M8/M74 Eastbound link bridge.
East Section (Polmadie to Fullarton Road)
Earthworks
Rutherglen Station
The import of fill materials has progressed at around 10,000m3 per week so 67,325m3 of 181,090m3 are now in place. In addition the embankment piling on the approach to Rutherglen Station Bridge is underway.
Cambuslang Road
The import of fill materials has also commenced at Cambuslang Road with 55,657m3 of 102,287m3 now in place.
River Clyde
Between Cambuslang Road and the Clyde works are progressing on three fronts:
Mineworkings
Remediation of historically discarded paper pulp through mixing with PFA (Pulverised Fuel Ash) and lime
Bulk import of fill materials
Fullarton Road
Grouting at Fullarton Roundabout to the east of the Clyde is nearing completion. Bulk fill has commenced with 55,937m3 of the 191,599m3 of material now in place.
Pre-Earthworks Drainage
Glasgow Road
In the past month this area has been the focus of drainage operations.
Culverts
Scion
The construction of culverts is ongoing at present with some up to 8 metres deep.
Battleburn Culvert
The culvert at Battleburn is now complete.
Structures
Glasgow Road
Piling to the piers and the West abutment of this structure is now complete. The pier bases and columns have subsequently been poured.
Farmeloan Road
The deck of the underbridge at Farmeloan Road is now in place and work on the parapets well underway.
Cambuslang Road
This structure is progressing on schedule with the West abutment and East pier bases now cast.
Auchenshuggle
Here the sheet piling scour protection, which provides protection against erosion from the river’s current, is complete and piling is ongoing at the East abutment.
West Section (Kingston Junction to Polmadie)
Paisley Road Off-Ramp
The first traffic switch has been implemented and is working smoothly.
M8/M74 Eastbound Link Bridge
Bored piling is now complete at piers two and three and the East abutment. Crane platforms are now being prepared to enable the erection of the bridge beams.
M8/M74 Westbound Link Bridge
Piling work on the foundation of the piers is ongoing and construction of the piers is now imminent.
Port Eglinton Viaduct
Piling work is ongoing with eight piers now complete and the West abutment progressing well. Foundations laid, structural concrete work has now commenced on several piers and columns are being constructed.
Strathbungo Railway Underpass
Works at the underpass are ahead of schedule with groundworks and piling ongoing. The approach embankment to the east side of the underpass is complete.
Polmadie Road Bridge
Pre-cast embankment piling has been completed and flared heads are underway. Service diversions are being prepared.
Rutherglen Railway Station Bridge
Clearance and preparation of the site of the bridge Station is now underway including the completion of pre-earthworks drainage.
Polmadie
Ground consolidation works in advance of the erection of the retaining walls at the junction are now complete.
Cathcart Road Bridge
The required service diversions are now fully in place, the traffic switch is running smoothly and work on the piled foundations for the bridge will begin shortly.
East Section (Polmadie to Fullarton Road)
Glasgow Road
In the Glasgow Road area contaminated soil has been removed for treatment to allow work on the embankments to progress. The foundations of the embankment have been completed and the starter layer of fill is now in place while the installation of band drains and pre-earthworks drainage is ongoing.
Rutherglen Station
Pre-earthworks drainage is now complete and embankment piling on the east side of the station is progressing.
Farmeloan Road Bridge
Work is now underway on the erection of bridge beams at Farmeloan Road.
Cambuslang Road
Pre-earthworks drainage and embankment works in the area are
progressing well and building of the Eastfield Culvert underway. The west column base of Cambuslang Road Underbridge has been constructed.
River Clyde area
Earthworks are proceeding well on three sites between Cambuslang Road and the River Clyde with drilling and grouting 70% complete and pre-earthworks drainage underway. Work on Battleburn Culvert has also commenced.
West Section (Kingston Junction to Polmadie)
The Paisley Road off ramp has reopened to traffic.
At the M8/M74 Eastbound Link Bridge pier three has been piled. The infill to the east abutment, which supports the ends of the bridge structure, is complete. Sheet piling is underway on pier one whereby sheets of steel are driven into the ground to provide support for the bridge’s foundations. Piling will continue to July with the deck of the bridge due for completion in October.
From Carnoustie Street to West Street the embankment fill is now at its full height.
Work is well underway on the Port Eglinton Viaduct. At West Street piling work on the west abutment is ongoing. On the east side of West Street pier one has been piled and preparation work is underway on its bases. At pier two the piling platform, the working platform from which piling is installed, is now in place with work due to start in a few weeks time. Bored piling work is ongoing at piers three and four (between Paisley and City Union Line) while at pier five (at the east side of City Union Line) the base has been completed as have the bases for piers six, seven and eight. The columns for pier eleven are now complete with construction ongoing on the columns at pier ten. Temporary trestles are being put in place in Falfield Street to provide support for the structure during construction.
At Strathbungo Embankment work is underway to prepare the starter layers to accept the fill that will be used, a process which takes around a month. Work will also commence shortly to prepare the piling platform for driven piling which again will take around one month to complete.
Mineworkings and grouting on the east side of Cathcart Road are almost complete. There will be a diversion in place in mid-February on the east side of the existing road to allow construction of the overbridge to progress.
Grouting will be ongoing at the site of Dixons Blazes off Cathcart Road until June.
At Polmadie Road Underbridge East and West pre-cast concrete piling will shortly be complete to be followed by the construction of the piers and filling of the abutment. The beams for the bridge are due to be in place by summer 2010.
East Section (Polmadie to Fullarton Road)
Earthworks have commenced at Glasgow Road West with contaminated material being moved into soil treatment centres. This phase of driven piling to the embankment has one week to go, currently being 65%complete. Installation of band drains, which accelerate the settlement of the soil, has also started and is expected to last for two weeks.
At Glasgow Road East, again driven piling to the embankment has is nearly complete. Service diversions on the northbound side of the road have been completed and work is now ongoing on the southbound side, due for completion shortly.
The new road at Quay Road is opening early March. Drainage works at Glasgow Road and Queen Street have commenced and will last for six weeks.
At Rutherglen Station the east side piling platform is complete and driven piling will be commencing the first week in February.
Work is progressing well on the Farmeloan Road Underbridge. The earthworks for the piling for the abutments are now complete. The base excavation to the west pier of the bridge is now done, with steelfixing, which reinforces the structure, commencing this week. Passersby will be able to see the changing landscape with the columns for the bridge being completed very shortly. The fill to the embankment on the east side is now complete and piling can commence. The import of material to fill the remaining embankment will start after Easter and will take a number of months to complete.
At Cambuslang Road the west pier of the bridge has been piled with the first phase of the new road construction nearing completion; piling will recommence in early February.
Duchess Place will be open to traffic in early February. This will enable Cunningham Road to be closed so that access can be gained to complete the Cambuslang Road West embankment piling.
Going east along Cambuslang Road there will be earthwork operations up to the site of the Corus yard which will be ongoing until Easter; this includes the commencement of the installation of band drains starting mid March. Grouting works will be ongoing on the section of the road from Corus to Clyde until mid May.
Construction of the Auchenshuggle Bridge, which will carry the motorway over the Clyde, is due to start just before Easter. Grouting works will begin shortly at the Fullarton Road roundabout.
West Section (Kingston Junction to Polmadie)
Work on the Port Eglinton Viaduct and the surrounding area is progressing well. The Paisley off-ramp has been kerbed and binder laid on the road surface. Construction of the tie-ins, where the new road joins with the existing road, will start towards the end of January and beginning of February 2009.
At the M8/M74 Eastbound Link Bridge piling preparation is ongoing as is the filling of the Kingston embankment.
At the Port Eglinton Viaduct piling of the west abutment has now started. Seven of the viaduct’s 14 piers have now been piled and four bases have been cast; work has also begun on one of the columns that will support the bridge deck.
Mining consolidation on both sides of Cathcart Overbridge are ongoing, as are service diversions.
At Polmadie Underbridge the majority of fill is now in place on the west side with piling due to start mid-January. On the east side the piling process is ongoing with a completion date of mid-January.
East Section (Polmadie to Fullarton Road)
At Glasgow Road Underbridge piling is now underway on the west wide with it and the ongoing piling on the east side of the bridge due to be completed mid-February 2009.
The fill has now been completed to the level of the abutment at both the east and west sides of Farmeloan Road Underbridge and drainage is in place at Quay Road.
Construction is progressing on the west side of Cambuslang Road Underbridge and embankment piling, service diversions and drainage are ongoing. On the east side of the bridge some of the bored piling is now complete and work is continuing on the driven piling.
Mining consolidation is ongoing for the remainder of the East section of the route up to Fullarton Road.
West Section (Kingston Junction to Polmadie)
Earthworks at the Paisley Road off ramp are now complete.
At Gloucester Street embankment piling, the construction of a structural support, is 70% complete and 25% of the imported fill required for this structure is in place. At Strathbungo embankment the installation of band drains is complete while mining consolidation is ongoing.
Five of Port Eglinton Viaduct’s 14 piers have now been piled and two bases have been poured.
Service diversions at Cathcart Rd have commenced while at the Cathcart cut to Polmadie Road, excavation and filling is taking place with lime stabilisation being applied to fill material. The installation of band drains at Polmadie is complete.
East Section (Polmadie to Fullarton Road)
Service diversions at Glasgow Road, Cambuslang Road and Quay Road are underway. The installation of piezometers, which measure how far below the surface groundwater is located, and inclinometers, sensors which measure any change in angles, is now complete at Glasgow Road and Cambuslang Road. The Quay Road diversion is kerbed and awaiting surfacing and contaminated soil will be moved to a soil treatment centre.
At Farmeloan Road overbridge embankment the driven piles are complete and embankment fill, drainage and structural piling is now underway. Site clearance from Farmeloan Road to Cambuslang Road is ongoing as is mining consolidation from Cambuslang Road to Fullarton Road.
Duchess Place is currently awaiting surfacing.