The Cathcart Road overbridge will carry Cathcart Road over both carriageways of the M74 allowing motorway traffic to pass below Cathcart Road, leaving this important local road back on its pre-existing route unaffected by the new motorway.
The two span bridge will be built using ‘top-down’ construction methods. To do this, existing services will be diverted and a temporary realignment of Cathcart Road will be constructed to the east of the existing road. Once traffic has been diverted on to this, reinforced concrete piles to support the west half of the new bridge will be constructed. The reinforced concrete deck for the new bridge will be cast on to these piles, using the existing ground to support the deck until it has gained strength. Traffic will then be diverted onto the west half of the deck and a similar process followed for the east section.
There will be some minor impacts on existing traffic using Cathcart Road during construction but this construction method will minimise disruption and allow two-way traffic to be maintained at all times.
| ID | Task Name | Start | Completion |
|---|---|---|---|
| 1 | Cathcart Road Overbridge | Late 2008 | Spring 2011 |
| 2 | Temporary Works (Falsework & Formwork) | Late 2009 | Summer 2010 |
| 3 | Preparations for Road and Services Diversions | Late 2008 | Summer 2009 |
| 4 | Cathcart Services - Temporary Service Diversions/Protection | Late 2008 | Autumn 2009 |
| 5 | Bridge Construction Phase 1 - West | Autumn 2009 | Spring 2010 |
| 6 | Bridge Construction Phase 2 - East | Spring 2010 | Autumn 2010 |
| 7 | Cathcart Services - Permanent Service Diversions/Protection | Spring 2010 | Early 2011 |
| 8 | Landscape, Planting and Seeding Works (Cathcart Road) | Early 2011 | Early 2011 |
| 9 | Substructure (Following Excavation) | Early 2011 | Spring 2011 |