Farmeloan Road Underbridge

Farmeloan Road underbridge
Aerial view of Farmeloan Road underbridge

The Farmeloan Road underbridge will carry both carriageways of the M74 over the existing Farmeloan Road, leaving traffic on Farmeloan Road unaffected by the finished motorway.

The three span bridge is supported at each end by reinforced concrete supports (abutments) and at two intermediate locations by multiple circular reinforced concrete columns (piers). The bridge deck (superstructure) is made up of precast concrete beams with reinforced concrete cast in place over the beams. Once the main superstructure is in place, follow on works (finishes) are required to complete the parapets, waterproof the bridge and lay the road surfacing ready for use.

There will be some minor impact to traffic on Farmeloan Road during construction of the bridge and the erection of the bridge beams. Short overnight and/or Sunday closures of Farmeloan Road will be required when the bridge beams are being lifted into position.

Timeline
ID Task Name Start Completion
1 Farmeloan Road Underbridge Autumn 2008 Summer 2010
2 Foundations Autumn 2008 Early 2009
3 West Abutment Foundation Autumn 2008 Early 2009
4 East Pier Foundation Autumn 2008 Late 2008
5 West Pier Foundation Autumn 2008 Early 2009
6 East Abutment Foundation Autumn 2008 Early 2009
7 Substructure Autumn 2008 Late 2008
8 Superstructure Early 2009 Spring 2009
9 Finishes Phase 1 Early 2009 Summer 2009
10 Finishes Phase 2 Summer 2010 Summer 2010

Back to The Route

No votes yet
Visit Us On: Follow us on Flickr Follow us on Twitter Watch and subscribe to our YouTube channel


Contact us

Please view the project contact details if you have an enquiry specific to the M74 project.

If you wish to make a more general enquiry, please view the contact information page for details