Glasgow Road Underbridge

Glasgow Road underbridge
Aerial view of Glasgow Road underbridge

The Glasgow Road underbridge will carry both carriageways of the M74 over the existing Glasgow Road, leaving traffic on Glasgow Road unaffected by the finished motorway.

The three span bridge is supported at each end by reinforced concrete supports (abutments) and at three intermediate locations by multiple circular reinforced concrete columns (piers). The bridge deck (superstructure) is made up of precast concrete beams with reinforced concrete cast in place over the beams. Once the main superstructure is in place, follow on work (finishes) will complete the parapets, waterproof the bridge and lay the road surfacing.

There will be some minor impact to traffic on Glasgow Road during construction of the bridge and the erection of the bridge beams. Short overnight and/or Sunday closures of Glasgow Road will be required when the bridge beams are being lifted into position.

Timeline
ID Task Name Start Completion
1 Fullarton Road Structures Summer 2009 Autumn 2010
2 Fullarton Road East Bridge Summer 2009 Summer 2010
3 East Abutment Summer 2009 Early 2010
4 West Abutment Summer 2009 Spring 2010
5 Superstructure Spring 2010 Summer 2010
6 Fullarton Road West Bridge Summer 2009 Summer 2010
7 East Abutment Summer 2009 Spring 2010
8 West Abutment Autumn 2009 Spring 2010
9 Superstructure Early 2010 Summer 2010
10 Superstructure Finishes Summer 2010 Autumn 2010
11 Eastbound Finishes Summer 2010 Summer 2010
12 Westbound Finishes Summer 2010 Autumn 2010

Back to The Route

Your rating: None Average: 1 (1 vote)
Visit Us On: Follow us on Flickr Follow us on Twitter Watch and subscribe to our YouTube channel


Contact us

Please view the project contact details if you have an enquiry specific to the M74 project.

If you wish to make a more general enquiry, please view the contact information page for details