The Port Eglinton viaduct is the largest bridge being constructed as part of the M74 Completion. It will carry both carriageways of the M74 over a number of surface streets and rail lines. From west to east, these are:
The construction of this bridge will mean that all existing rail lines and local roads that the M74 extension crosses in this area are retained following completion of the new motorway.
The 12 span bridge is supported at each end by reinforced concrete supports (abutments) and at ten intermediate locations by multiple circular reinforced concrete columns (piers). The bridge deck (superstructure) is made up of steel box girder beams with reinforced concrete cast in place over the beams. Once the main superstructure is in place, follow on works (finishes) will complete the parapets, waterproof the bridge and lay the road surfacing.
Following completion of the bridge supports, the steel box girders will be lifted onto the supports by large cranes, except for the section over the Cathcart Circle/West Coast Main Line rail lines and Pollokshaws Road where the beams will be ‘launched’ over the roads and rail lines by pushing with jacks. Two major temporary steel trestle supports will be erected either side of the rail lines to assist in temporarily supporting the bridge when it is being launched.
| ID | Task Name | Start | Completion |
|---|---|---|---|
| 1 | Port Eglinton Viaduct Structure | Mid 2008 | End 2010 |
| 2 | Substructure | Mid 2008 | Early 2010 |
| 3 | Pier 11 Devon Street | Mid 2008 | Late 2008 |
| 4 |
Pier 10 Devon Street |
Mid 2008 | Early 2009 |
| 5 | Pier 3 Royal Mail yard | Autumn 2008 | Early 2009 |
| 6 | Pier 4 Royal Mail yard | Autumn 2008 | Spring 2009 |
| 7 | Pier 2 East of West Street | Autumn 2008 | Spring 2009 |
| 8 | Pier 1 East of West Street | Late 2008 | Mid 2009 |
| 9 | West Abutment - West Street | Autumn 2008 | Autumn 2009 |
| 10 | Pier 8 Stromness Sreet | Autumn 2008 | Early 2010 |
| 11 | Pier 7 Mauchline Street | Summer 2008 | Early 2010 |
| 12 | Pier 6 Mauchline Street | Summer 2008 | Early 2010 |
| 13 | Pier 5 Mauchline Street | Autumn 2008 | Early 2009 |
| 14 | Temporary Trestle 1 Stronmess Street | Autumn 2008 | Early 2009 |
| 15 | Pier 9 Salkeld Street | Autumn 2008 | Spring 2010 |
| 16 | East Abutment Pollokshaws Road | Early 2009 | Late 2009 |
| 17 | Temporary Trestle 2 Eglinton Street | Early 2009 | Summer 2009 |
| 18 | Structural Steelwork Site Works | Spring 2009 | Mid 2010 |
| 19 | Deck Construction | Summer 2009 | Late 2010 |
| 20 | Roadworks - Eastbound | Summer 2010 | Autumn 2010 |
| 21 | Roadworks - Westbound | Summer 2010 | Autumn 2010 |