Construction Progress

July 2010

Auchengeich Road Bridge  

Auchengeich Road Bridge
The concrete deck of the Auchengeich Road Bridge was completed in late June 2010, following a busy period of erecting the temporary support structure and installing the reinforcement steel. Works to this new bridge commenced in February 2010, with the permanent bridge supports completed by April 2010. The finishing works for the structure should be complete by September 2010.

Filling works will be ongoing on the approaches to the new bridge throughout the summer months to allow construction of the new road. It is currently targeted that the works will be complete by December 2010 which will allow the opening of Auchengeich Road.

Glenview Bridge

Aerial photo of the Glenview Bridge
with one lane open for traffic
Works to Glenview Bridge are now substantially completed with one lane of the bridge opened to traffic, controlled by traffic lights, in late June 2010. Pedestrians and cyclists are also able to use the bridge which should be fully opened to two-way traffic by the end of July 2010. The reconstruction of Glenview Bridge was carried out in 4 phases which involved complex traffic management schemes to minimise the disruption to traffic flows on the existing A80, over which Glenview Bridge spans.

The 4 phases of the works were as follows:

  • Demolition of existing bridge in August 2009
  • Diversion of A80 traffic towards the centre of the carriageway to allow construction of the new North and South abutments
  • Once the new abutments were complete, the traffic on the A80 was then diverted to the outside carriageways to provide a safe working space to construct the new central pier
  • Installation of prefabricated steel deck beams was successfully carried out over the weekend of 10th April, 2010, and this allowed the subsequent insitu concrete deck construction works to commence

Deck concrete was completed in early May 2010, and works to the parapets and deck finishes progressed well throughout May. The associated tie-in works to Glenview Avenue continued throughout June, and final completion of all the finishing works should allow two-way traffic over the bridge by the end of July 2010.

Spring 2010 update

Stepps to Mollinsburn

Road construction at the Hornshill Interchange area is progressing well. Works are ongoing in the verges and a traffic management switchover is targeted for May 2010, to complete centre carriageway works.
Construction has already commenced on the Hornshill B757 link road which is due to be completed by mid-summer 2010.

The main M80 carriageway construction, from the Hornshill Junction to Lindsaybeg Road, remains on programme to be complete by late autumn 2010.

Mollinsburn Interchange

Mollinsburn Interchange - aerial view
west

The new Mollinsburn Interchange is one of the most complex sections of the M80 Project. At this new interchange the M80 provides links to the M73 and surrounding local access roads to Westfield, Mollinsburn and Gartferry. Works to complete the interchange will be ongoing throughout 2010. Works on the M73 will recommence in May 2010 with major works continuing throughout the summer months.

New Hornshill Junction Overbridge

Construction of this bridge is well advanced with the concrete deck formed in March; this will now be followed by finishing of the deck edges and backfill to the bridge abutments.

Lindsaybeg Road Overbridge

Works are well underway at this bridge with pier construction complete and earthworks operations commencing to allow construction of the concrete end supports to the bridge. Overall structural completion is due late summer, with the new Lindsaybeg Road, B819, to be completed by late autumn.

Kelvin Valley Footbridge

Piling works and the construction of the end support slabs have now been completed and are ready for the installation of the structural steelwork which is to be erected in July 2010.

Auchengeich Road Overbridge

Following completion of the bridge substructure, erection of temporary supports for construction of the concrete bridge deck is due to be completed during April and May. Overall structural completion is programmed for late August 2010.

Mollinsburn Link Overbridge - temporary
supports in place for concrete deck
construction

Mollinsburn Link Overbridge

The concrete deck was formed in late March and the removal of temporary supports will commence after the concrete has gained sufficient strength. Following completion of the deck works the road carriageway construction will commence.

M73/M80 Link Overbridge

Works are now well advanced following the installation of steel bridge beams to the M73/M80 link overbridge. Construction of the deck is now underway with the concrete deck pour planned for mid-May.

Mollinsburn Overbridge

Following the installation of the steel bridge beams and completion of on-site welding operations, the temporary support has now been removed, allowing traffic restrictions to be reduced. Earthworks operations will commence behind both ends of the bridge during April 2010.

Mollinsburn to Auchenkilns

Construction works between the Mollinsburn Interchange and the Auchenkilns interchange are now well advanced. The construction of the new northbound carriageway is targeted for completion by late spring 2010, which will allow traffic to be switched and the construction of the new southbound carriageway to commence. The A80 Low Woods diverge to the A8011 was closed for a period of approximately 10 weeks, commencing in April, to enable construction of the new slip road.

Luggie Water Culvert - temporary works
for abutment construction

Luggie Water Culvert

Construction of the end supports to the northern structure are currently underway and the installation of concrete deck beams is planned for late April. Following this, earthworks and carriageway construction will be undertaken and both A80 northbound and southbound traffic will be diverted over this structure. Following this traffic diversion, construction of the southern section of this crucial structure will commence with the aim to alleviate this bottle-neck restriction within the site.

North Road Overbridge

Steel bridge beams were erected in March over the future M80 northbound carriageway. The construction of the south end supports is nearing completion, and once traffic is diverted onto the new northbound carriageway the remaining beams are planned for erection over the southbound carriageway in early summer 2010.

Auchenkilns to Haggs

Roadworks from Auchenkilns to Haggs have been ongoing since April 2009 and are well advanced on the new southbound carriageway. Southbound verge widening works from Haggs to Castlecary Arches are continuing whilst works on the northbound carriageway will commence in summer 2010.

Dullatur Road Underbridge

Construction works to the edge of the southbound bridge were completed in March 2010 with traffic now switched to facilitate works to the central reserve. Demolition works for removal of the existing central reserve edge beam on the southbound deck are complete.

Old Inns Underbridge

The central reserve edge beams to both the southbound and northbound decks have been completed with works ongoing on the central reserve deck slab. Works to the edges of both the southbound and northbound bridges will commence simultaneously once the central reserve is completed and traffic switched.

Forest Road Underbridge - installation
of surfacing immediately prior to
traffic switch

Forest Road Underbridge

Construction works to the edge of the southbound bridge were completed in February with traffic switched to this side to facilitate works to the central reserve. Demolition works for the removal of the existing central reserve edge beam are currently ongoing.

Castlecary Viaduct Pier Protection

Works to construct protection to the Viaduct pier, adjacent to Walton Road, have commenced and future traffic management will facilitate the completion of these works and the commencement of works to the A80 southbound carriageway.

Glenview Bridge, looking north

Glenview Avenue Overbridge

The bridge supports have been completed and the steel deck beams have been erected. Works to complete the concrete deck are ongoing.

Kilsyth Road Overbridge

Site investigation works to confirm the existing bridge details and the position of utilities crossing the bridge have been completed. Construction works for new approach walls and parapets will commence in May. Traffic management has been installed during nightshifts in preparation of construction works.

Haggs Retaining Wall

Structural concrete works to this retaining wall have been completed, with waterproofing and finishes currently underway prior to installation of wall drainage and backfill.

Redburn Culvert Extension

Works are well established with piling and foundation works progressing in the burn and adjacent to the Castlecary Viaduct. On completion of piling works, reinforced concrete retaining walls and a deck slab will be commenced. Upon completion of the culvert extension reinforced earth abutments will be constructed to allow the re-alignment of Castlecary Road through the arch adjacent to the current road alignment.

For previous  reports see Construction Progress Archive.

Visit Us On: Follow us on Flickr Follow us on Twitter Watch and subscribe to our YouTube channel

Please view project contact details if you have an enquiry specific to the M80 project.

If you wish to make a more general enquiry, please view the information about Transport Scotland for details.