Timeline

For the start date and completion date of the project see the programme document.

ID  Task Name  Start  Completion 
M74 Programme  May 2008  June 2011 
Construction Start  May 2008  n/a 
M8/M74 Eastbound Viaduct  August 2008  Spring 2010 
4 M74/M8 Westbound Viaduct  September 2008  Summer 2009 
Port Eglinton Viaduct  June 2008  Spring 2011 
Strathbungo Rail Underpass  November 2009  Late 2010 
Cathcart Road Overbridge  July 2008  Spring 2011 
Polmadie Road Underbridge  October 2009  Spring 2011 
Glasgow Road Underbridge  February 2010  Early 2011 
10  Rutherglen Station Underbridge  May 2009  Autumn 2010 
11  Farmeloan Road Underbridge  June 2008  Spring 2010 

12 

Cambuslang Road Underbridge  November 2008  Late 2009 
13  Auchenshuggle Bridge (Clyde Crossing)  May 2009  Early 2011 
14  Fullarton Roundabout West Bridge  January 2010  Autumn 2010 
15  Fullarton Roundabout East Bridge  February 2010  Autumn 2010 
16  General Roadworks  May 2008  Summer 2011 
17  Project Completion  n/a  June 2011
Your rating: None Average: 4 (20 votes)
Visit Us On: Follow us on Flickr Follow us on Twitter Watch and subscribe to our YouTube channel


Trunk Road Projects

Looking for further details of motorway and trunk road improvement projects across Scotland?


Or view all trunk road projects »


What's New


Register for the Newsletter

Register to receive the M74 Completion newsletter