The southern approach viaduct to Kincardine Bridge has deteriorated, is propped temporarily and requires reconstruction in the medium term.
Existing traffic flows in Kincardine cause noise, pollution, visual intrusion, road safety dangers and severance for the local community.
Peak traffic flows far exceed the capacity of the roundabout in Kincardine resulting in delays to traffic and rat-runs through the local streets.
The preferred option for a new crossing at Kincardine is:
To deliver some early traffic relief to Kincardine, the Eastern Link Road (ELR) is being promoted ahead of the main crossing.
Main Crossing Study
The consultants taking forward the project - the Babtie Group and Faber Maunsell - have completed their comparative assessment of the alternative routes considered for the new crossing.
The preferred route which will be provided through Statutory Procedures is that through the former Kincardine Power Station. The line of the proposed route is shown below
This route performed better compared to the alternatives when assessed overall against the criteria of Environment, Economics, Safety, Accessibility and Integration.
The scheme will involve:
The necessary Road Orders and Compulsory Purchase Order were made on 5 July 2002.
An artist's impression of how the road will look is shown below.
Contractors are now pricing the construction work and are due to submit their tenders in February 2003.
A contract is expected to be awarded in the Spring and construction work will start in the Summer. Further information relating to the construction phase of the project will be provided nearer the time.
|
ACTIVITY |
ESTIMATED DATE |
|---|---|
| Eastern Link Road Construction Start | Summer 2003 |
|
Publication of Draft Road Orders for the Main Crossing, including public exhibition of proposals |
Summer 2003 |
Further progress on the main crossing will depend on the public reaction to the published proposals.
Looking for further details of motorway and trunk road improvement projects across Scotland?