13.3.3.2 Step 2: Identifying the Stage of Scheme Development

Publication Date: 
27 May 2008

The Department for Transport has identified three main stages in the life of a transport project and provided default uplift values for each (uplift values for rail projects are presented separately in Section 13.3.4). These stages are illustrated in Table 13.3. Practitioners should note that these stages are indicative of the quality of Risk Assessment and cost estimate typical of schemes at the different stages of development.

Table 13.3: Scheme Development Stages

Category

Stage 1

Stage 2

Stage 3

Local authority and Public Transport Schemes

Programme Entry

Conditional Approval

Full Approval

Major Road Schemes

TPI entry/ Preferred Route Decision

Order Publication/Works Commitment

Works Commitment